ameO <br />D) Overburden Fill Placement <br />Overburden fill material was delivered from CC &V Mine Operations throughout both day and night <br />shifts. Ames CAT D -10 dozers were used to maintain the borrow area. A CAT 993 front -end <br />loader and a CAT 992 front -end loader were used to load overburden fill material into CAT 40 -ton <br />articulating, CAT 773, and CAT 777 haul trucks. <br />Overburden fill was placed in the areas shown on Figure 1. Overburden fill was placed in 36" to <br />40" loose lifts using various CAT dozers, keying into existing slopes when necessary. Various <br />CAT excavators with a hammer attachments "broke up" oversize boulders before they were <br />placed in the fill. Each lift was moisture conditioned using a CAT 773 water truck (when <br />necessary) and compacted using a 10 -ton vibratory smooth drum compactor, passing over the <br />entire fill surface at least 4 times (method compaction technique was applicable). <br />E) Slope Contouring <br />Slope contouring was performed using a John Deere 850 excavator. Material generated during <br />slope contouring was placed as overburden fill at the top of the slope. <br />F) Soil Liner Fill (SLF) <br />Setup of the SLF processing plant at the East Cresson Clay borrow was performed during. <br />Processing is scheduled to begin Monday May 28, 2012. <br />G) Drain Cover Fill (DCF) <br />Drain Cover Fill (DCF) placement was performed covering the existing exposed Phase IV <br />geomembrane. DCF was hauled to the area using CAT 40 -ton articulating haul trucks loaded by a <br />CAT 988 front -end loader. The DCF was placed in a two foot lifts using a CAT D -6 dozer. Pipe <br />bedding material was also placed over the HDPE pipe in the area using the same process. <br />Location <br />This Week <br />Cumulative <br />Comments <br />(tons) <br />(tons) <br />DCF Process <br />- <br />158,613 <br />DCF processing is temporarily paused <br />Total <br />- <br />158,613 <br />DCF processing is temporarily paused <br />H) Miscellaneous <br />No work performed during the week. <br />II) Underground Mine Workings <br />A) Discovery <br />No new Underground Workings were encountered during the week. <br />B) Drilling <br />Confirmatory drilling was performed at Underground Working #4081 using two track mounted drill <br />rigs. A drill pattern was set out by an AMEC field representative. Eighty holes were drilled <br />encountering twenty -one voids. An approximate total of 4,000 linear feet was drilled. As -built <br />survey of the drill holes was performed by Ames. <br />Blast pattern drilling was performed at Underground Workings #4052 and #4058, preparing to <br />collapse a portion of the crown pillar. <br />MEW Weekly Report WE 05.26.2012 <br />