TR -109 Response Cont. <br />Page 2 of 3 <br />The first item found was within the findings documents associated with each bond <br />release. A discrepancy was found within these documents, prepared by the division, <br />concerning the total released acreage for Phase II bond release SL -6. Trapper ultimately <br />requested a total bond release of 819.5 acres. Division calculations within the findings <br />document indicate the release should have been 819.6 acres. Current tabulations of the <br />released parcels show the release was comprised of 819.6 acres, however, the findings <br />document summaries show an official release of 819.1 acres. This acreage appears to be <br />a typographical error. <br />The division currently shows total Phase II bond release at 3,573.0 acres; however, this <br />total is in error due to the above error in total bond release for SL -6. Trapper would like <br />to request that the official release for SL -6 be revised to 819.6 acres as originally <br />intended. <br />A second item found was that one of the primary discrepancies between the Trapper total <br />Phase II bond release and the Divisions total is also within SL -6, involving Parcel A -B- <br />98. This particular parcel received Phase I bond release during SL -5 at 50.7 acres. With <br />the submittal of SL -6 a sub - parcel of A -B -98, south of Life of Mine road was removed <br />from the bond release due to projected re- disturbance. Therefore A -B -98 was released at <br />40.5 acres in SL -6. However, the entire sub - parcel was not fully disturbed as <br />anticipated. Only 5 acres of this sub - parcel was disturbed. During SL -10, Trapper <br />requested Phase III Bond release of 45.7 total acres for this parcel. Due to this request, <br />5.2 acres of this parcel received Phase III release but not Phase II. Trapper had been <br />erroneously carrying this additional 10.2 acres in its total Phase II amount. <br />Trapper would like to request that these 5.2 acres be granted Phase II bond release status <br />as they have already received Phase III bond release status. Due to the small <br />discrepancies noted here, Trapper does not request any change in liability, but to simply <br />address the total acres as noted. <br />An additional sub - section will be added to Section 1.0 of the annual report. Sub - section <br />1.2.7 shall include a description of re- disturbance activities and an additional table, titled <br />Table 1.2, shall demonstrate acreage changes and bond release status for each parcel <br />affected. New material for section 1.0 and the additional Table 1.2 are attached. <br />A summary of current bond release acres is as follows (current for 2011, does not <br />include recent releases of SL -12 and SL -13): <br />DRMS <br />Current <br />Totals <br />Trapper Mine <br />Adjusted Totals <br />Total <br />Re- disturbance <br />acres <br />New Total <br />Bond Release <br />Acres <br />Phase I <br />3870.0 <br />3870.0 <br />24.8 <br />3845.2 <br />Phase II <br />3573.9 <br />3574.4 <br />17.5 <br />3556.9 <br />Phase III <br />2925.5 <br />2925.5 <br />5.9 <br />2919.6 <br />TR -109 Response Cont. <br />Page 2 of 3 <br />The first item found was within the findings documents associated with each bond <br />release. A discrepancy was found within these documents, prepared by the division, <br />concerning the total released acreage for Phase II bond release SL -6. Trapper ultimately <br />requested a total bond release of 819.5 acres. Division calculations within the findings <br />document indicate the release should have been 819.6 acres. Current tabulations of the <br />released parcels show the release was comprised of 819.6 acres, however, the findings <br />document summaries show an official release of 819.1 acres. This acreage appears to be <br />a typographical error. <br />The division currently shows total Phase II bond release at 3,573.0 acres; however, this <br />total is in error due to the above error in total bond release for SL -6. Trapper would like <br />to request that the official release for SL -6 be revised to 819.6 acres as originally <br />intended. <br />A second item found was that one of the primary discrepancies between the Trapper total <br />Phase II bond release and the Divisions total is also within SL -6, involving Parcel A -B- <br />98. This particular parcel received Phase I bond release during SL -5 at 50.7 acres. With <br />the submittal of SL -6 a sub - parcel of A -B -98, south of Life of Mine road was removed <br />from the bond release due to projected re- disturbance. Therefore A -B -98 was released at <br />40.5 acres in SL -6. However, the entire sub - parcel was not fully disturbed as <br />anticipated. Only 5 acres of this sub - parcel was disturbed. During SL -10, Trapper <br />requested Phase III Bond release of 45.7 total acres for this parcel. Due to this request, <br />5.2 acres of this parcel received Phase III release but not Phase II. Trapper had been <br />erroneously carrying this additional 10.2 acres in its total Phase II amount. <br />Trapper would like to request that these 5.2 acres be granted Phase II bond release status <br />as they have already received Phase III bond release status. Due to the small <br />discrepancies noted here, Trapper does not request any change in liability, but to simply <br />address the total acres as noted. <br />An additional sub - section will be added to Section 1.0 of the annual report. Sub - section <br />1.2.7 shall include a description of re- disturbance activities and an additional table, titled <br />Table 1.2, shall demonstrate acreage changes and bond release status for each parcel <br />affected. New material for section 1.0 and the additional Table 1.2 are attached. <br />A summary of current bond release acres is as follows (current for 2011, does not <br />include recent releases of SL -12 and SL -13): <br />