Laserfiche WebLink
July 9, 2012 C-2009-087/Peabody Sage Creek Mine JDM <br /> <br /> <br /> <br />PM-6 Lower End Construction SCM-1A Construction <br /> <br />PM-6 Lower End at PECOCO Pond SCM-1 at PECOCO Pond <br /> <br />GENERAL MINE PLAN COMPLANCE: <br />At the time of the inspection, topsoil salvaging and storage was ongoing in the areas of drainage construction <br />permitted under TR4. The initial mining process is ongoing with a continuous miner working to construct the four <br />portal entries at the portal site. At the time of the inspection the grouting work at the portal canopies is near <br /> <br />completion. The small conveyor from the portal to the temporary coal handling facility area is ongoing. <br />Number of Partial Inspection this Fiscal Year: 0 <br />Number of Complete Inspections this Fiscal Year: 1 <br /> <br />611 <br />Page of <br /> <br /> <br />