i <br /> August 1996 Monthly Report <br /> Page 4 <br /> Access was gained to the Longfellow portal and a 4 inch <br /> diameter drisco-pipe was connected to the cofferdam installed <br /> previously by the DMG-Inactive Mine Closure Program. This <br /> pipe was also extended around the Koehler pond in order to <br /> isolate the pond for pH adjustment, drainage and potential <br /> cleaning. <br /> Work was started on constructing temporary upland diversion <br /> ditches around the Koehler pond and Longfellow and Koehler <br /> dumps. <br /> With these diversions, SGC can begin to characterize water <br /> quality, refine the plan for site remediation and gather <br /> information for bio treatment system design. <br /> Surveying for air photo site contour mapping was started. <br /> Available information was on contour intervals too large for <br /> adequate site planning. <br /> Monitoring information is attached. <br /> - London Mine Portals - Waste Dumps <br /> This is a "B" list project and work on it is being deferred <br /> pending results from implementation of the "A" list projects. <br /> Preliminary contact with the owner of this property has been <br /> made. <br /> - Pride of the West Tailings <br /> SGC has delineated the wetland disturbance for a Section 404 <br /> Permit application and submitted this delineation to the U.S. <br /> Army Corps of Engineers District Office for review. A <br /> completed permit application will be submitted upon acceptance <br /> of the delineation. <br /> Complicated ownership issues along with apparent Mined Land <br /> Reclamation Permit compliance issues at this site may delay <br /> any work plan implementation until the 1997 construction <br /> season. <br /> SGC continues to work toward a final access agreement with the <br /> site owners. <br /> - Sunnyside Mine Pool Mitigation - Alkaline Solution Injection <br /> This project was active throughout the month of August. At <br /> the end of the month, an operational modification was made to <br /> inject alkaline material at the secondary injection site in <br /> Sunnyside Basin based on field conditions. The conditions <br /> that precipitated this change are the availability of water to <br /> supply lime solution in a dissolved state to the mixing zone <br /> and a water rights "call" on the Animas River that prevented <br /> SGC from appropriating more water than was released from the <br /> American Tunnel bulkhead. <br />