Laserfiche WebLink
weekend days or holidays without prior approval of the PROJECT MANAGER. It is the <br /> Contractor's responsibility to schedule inspections with the Project Manager so as not to <br /> delay the work. The following items must be observed and approved by the PROJECT <br /> MANAGER before ^ror-eedir,, <br /> 1. Completion of excavation of the Ditch 8 footprint; <br /> 2. Initiation of topsoil placement in Ditch 8; <br /> 3. Initiation of Permamat 20OF installation; <br /> 4. Completion of Permamat 20OF installation; <br /> 5. Initiation of topsoil application over Permamat 200F; <br /> 6. Initiation of feeder and upper channel excavation; <br /> 7. Initiation of feeder and upper channel liner installation; <br /> 8. Initiation of adjacent area topsoil application and surface roughening; <br /> 9. Completion of Sutey Topsoil Stockpile surface roughening. <br /> 15 <br />