. r <br /> -9- <br /> V. Total Reclamation Costs <br /> 1 . Direct Costs <br /> Backfilling $2,515,199.00 <br /> Demolition 605,095.00 <br /> Revegetation 659,500.00 <br /> Loadout 342,318.00 <br /> Sutey Refuse Area 205,252.00 <br /> Tunnel to Wash Plant Conveyor 307,138.00 <br /> $4,634, <br /> 2. Indirect costs <br /> Public Liability Insurance @ 0.8 percent $ 37,076.00 <br /> Workman's Compensation @ .0127 58,858.00 <br /> Contractor's Performance Bond @ 0.7 percent 32,442.00 <br /> Job Superintendent 4290 hrs @ 20.00/hr 85,800.00 <br /> MLRD Administration @ 5.0 percent 231 ,723.00 <br /> Contractors Profit @ 10 percent $ 463,450.00 <br /> $ 909,349.00 <br /> 3. Total Reclamation Costs $4,634,502.00 <br /> + 909,349. 00 <br /> Total Bond $5,543,850.00 <br /> This total cost represents a substantial increase over the current bond, which <br /> is approximately $2. 5 million. Mid-Continent should examine these figures, <br /> provide evidence to lower costs where possible, and revise the bond as <br /> necessary. In addition to cost estimates, 'Mid-Continent should reappraise the <br /> property being used for bond in light of current economic conditions. <br /> /l jc <br /> 8117F <br />