Mid-Continent Complex Re-Vegetation Status September 9, 1997 <br /> Description Total Revegetated - Revegetated Remaining Remaining <br /> Acreage Steep - Mild - Steep - Mild <br /> Central Yard Area 51.2 0 0 0 51.2 <br /> Rock Tunnel Waste Pile 14.0 2 12 0 0 <br /> Tunnel Area to Central Complex 25.0 0 1 10 14 <br /> Mines 1-5 Portals& Pads 35.1 3.8 31.3 0 0 <br /> Lune Pad Downslopes 22.0 12 0 10 0 <br /> Road G 24.0 0 24.0 0 0 <br /> Road F 14.9 0 14.9 0 0 <br /> Road E 6.5 0 6.5 0 0 <br /> Road D 19.7 0 4.0 0 15.7 <br /> Road C 17.9 0 0 0 17.9 <br /> Road B 4.7 0 0 0 4.7 <br /> Road A 8.1 0 0 0 8.1 <br /> Road DA 3.5 0 3.5 0 0 <br /> Exploration Drill Road 7.4 0 7.4 0 0 <br /> Road Downslopes 41.2 15 0 26.2 0 <br /> Sutey Pile 46.2 7 39.2 0 0 <br /> Old Refuse Pile 13.6 3 8.6 0 2 <br /> Totals 355 42.8 152.4 46.2 113.E <br /> Total credit for revegetation work completed: <br /> Steep acres: 42.8 ac x 53345/acre= S 143.166 In reality, the DMG has not reseeded 42.8 steep acres. It is simple a <br /> credit according to the ratio of the total area done compared to the percentage of steep acres in the bond estimate. See task <br /> 1 discussion under column for Actual Cost for Remaining Work. <br /> Mild acres: 152.4 ac x S599/acre = S 91.287 <br /> Total credit = S234.453 of total task cost of 5459,836. <br /> Note: the steep slope reclamation has only been done in very small areas as part of an experimentation plan. It is very <br /> unlikely that 90 acres throughout the site will be reseeded. <br />