Laserfiche WebLink
December Monthly/41h Quarter 1999 Report <br /> Page 2 <br /> Confirmation of completion by CDPHE has been received for two of these projects— <br /> Surface Mill Tailings at Eureka and Ransom Tunnel. Sunnyside has not received <br /> confirmation of completion from CDPHE for the remaining five projects although <br /> Sunnyside submitted completion certifications in October, 1997. <br /> • Sunnyside Mine Pool Mitigation—Alkaline Solution Injection <br /> This project was not active in December of 1999. <br /> The water pool pH, at the American Tunnel bulkhead, was 4.88 and the bulkhead gage <br /> read 420.5 psi at the end of December. This would indicate that a rise in the mine pool <br /> occurred since the end of November (1 foot). Sunnyside will continue to monitor these <br /> parameters. <br /> "B List" Projects <br /> • Columbus Mine Portals— Mine Waste Dumps <br /> • London Mine Portals—Waste Dumps <br /> Work, permitting or arrangement for access is not planned until it becomes evident that <br /> the work plans for these projects require implementation. <br /> • Mayflower Facility— Upland Hydrological Control <br /> This project was completed in October, 1999 and accepted by DMG as complying with <br /> the Consent Decree work plans and MLR Standards in November, 1999. <br /> • Tailings Pond No. 4 Surface Drainage Modification <br /> This project was completed in November, 1999 and accepted by DMG as complying with <br /> the Consent Decree work plan and MLR Standards. Progress pictures for this project are <br /> attached <br /> • Tailings Pond No. 4 Upland Groundwater Diversion <br /> Sunnyside had been holding discussions with BLM to implement this project in exchange <br /> for an area to place material from their Lackawanna mill tailings remediation project. <br /> Since it became apparent that the work on this project would not be completed by BLM <br /> in the allotted time frame, Sunnyside assumed project construction. This project was <br /> completed in December but due to snow accumulation in the project area, project <br /> inspection by DMG will not be possible until spring. <br />