Laserfiche WebLink
The estimate also includes initial seeding and reseeding costs for the remaining 255,9 <br />acres. These costs are included in tasks 065, 066, 067, 068, 069, 070, 072 and 073. The <br />estimate has also retained reseeding costs for complete vegetation failures for the Partial <br />Phase ILBond Release area in task 074 (the vegetation failure rate for 100% over the <br />release area of 592.7 acres or 592.7 acres of potential reseeding). <br />With the proposed release of $1,693,918.00 and the resulting liability of 2,611,566.00, <br />the Division will retain enough bond monies to ensure the final reclamation of the site in <br />the event of permit revocation and bond forfeiture. <br />Please let me know if you have any questions or need any additional information. <br />