Access Portal Collapse Repair and Equipment and Stope Rock Removal Work Plan March 2, 2012 <br />May Day No. 1 <br />Day No. 1 using a skid steer or mucker, and will then use a front end loader to place the <br />rock or ore into a 10 -ton truck for transportation off site. Wildcat will not transport more <br />than four 10 -ton trucks from the site per day between the hours of 8 AM and 5 PM. <br />Hauling will not occur on the weekends. <br />Wildcat seeks administrative approval to perform Phase 1 work, and proposes to later submit a <br />plan for Phase 2 activities for review and approval by DRMS. Wildcat is contemporaneously <br />requesting that MSHA review this Work Plan, and will incorporate any feedback from MSHA <br />into the Work Plan before implementation. <br />EnviroGroup Limited <br />DEN 97, 749,013v3 2 -29 -12 <br />3 <br />