types, operator/operating efficiencies, support equipment, and overall reclamation time span had to be <br />determined. The following discussion provides the considerations utilized in determining the equipment • <br />fleet needed. <br />Production Shifts, One shift per day was used for topsoiling and finish grading. Two shifts par day <br />were used for open pit backfilling. Using two shifts per day would allow for preventative maintenance <br />and minor equipment repair to occur on third shift, if needed. Shifts were based on an eight-hour period <br />per shift. A conservative operating efficiency of 83 percent was used to account for decreased <br />productivity due to operator efficiency for scrapers. Fifty min/hr was used for dozers due to other <br />factors, taking darkness into consideration. <br />Equipment Type. The types of equipment selected were based on similar type equipment presently <br />operating at the mine site or could prudently be brought in for a job of this magnitude. Whenever <br />possible, Caterpillar equipment was used for reclamation due to widely published information regarding <br />costs and performance. All equipment costs were taken from those provided by DMG. Please see <br />appropriate worksheets for a list of all cost factors. Equipment performance was based on Cat <br />Handbook No. 30, EMF, Means, FPC, or otherwise as noted. <br />Equipment and operator performance factors were based on generally published and accepted criteria • <br />(see individual worksheetsl. Operator wages were all based on information supplied by DMG. <br />Reclamation Time Frame. A reasonable time frame for a job of this magnitude is estimated at <br />approximately 1300 hours for backfilling and grading, and 1100 hours for topsoiling. Assuming three <br />D11 dozers working two shifts per day backfilling and grading and four 637 scrapers topsoiling one <br />shift per day, total project time is estimated at S months. This is assuming some topsoiling overlaps the <br />backfilling and grading. <br />Indirect Costs <br />The following is an estimate of indirect costs associated with the reclamation of the Seneca II-W Mine. <br />Mobilization and Demobilization Costs. Mobilization and demobilization costs were based .on mobilizing <br />• <br />the major pieces of equipment. <br />• <br />PR-05 6 Revised 05/05 <br />