Laserfiche WebLink
CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />AMEC observed the structural fill placement. Ambient and fill temperatures were monitored during fill <br />placement. <br />AMEC observed pipe trench excavation and PBM placement. <br />Testing Summary <br />Laboratory testing continued (Particle Size Distribution, Atterberg Limits, Moisture- Density Relations, <br />Specific Gravity, Permeability, and Point Load testing) for sampled materials. <br />GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />No concerns <br />Summary of Planning Items: <br />Continue structural fill placement <br />Continue pipe trench excavation and PBM placement <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC&V :: <br />CC &V held a weekly construction meeting on October 25, 2011. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />Ames Construction: <br />None <br />Summary of Incidents /Accidents/Health & Safety Issues: <br />None <br />We trust the information provided clearly repres- is our findings and observations for the week ending <br />October 29, 2011. <br />Joseph Hickey, CQA Moni ate: October 29, 2011 <br />Approved By: <br />te: ,oc eivi/ <br />PSES Weekly Report WE 10.29.2011 <br />