<br /> Colorado Division of Minerals and Geology
<br /> -----------------------------------------
<br /> ESTIMATING FORM - STRUCTURAL DEMOLITION WORK
<br /> Task No.: 2 Prepared by ACS
<br /> Permit No.: M-99-051 Filename M051-2
<br /> Date ' n ° -7 7 Operation Rock School Lease Project
<br /> ------------------ --------------------------------
<br /> Permitting action New aplication
<br /> -------------------------------------------------------------------------------------------------------
<br /> Task description Demolish and remove surface facilities
<br /> -------------------------------------------------------------------------------------------------------
<br /> MEANS Location Adjustment: 107.206 of base unit costs - MEANS SITE WORK & LANDSCAPE COST DATA 1997 Edition
<br /> ------------------
<br /> I 1 I I MEANS BASEI ADJUSTED
<br /> STRUCTURE / FACILITY / EQUIPMENT DESCRIPTION DIMENSIONS I COMPOSITION I QUANTITY I UNIT I UNIT COST I TOTAL COST
<br /> I I I I I I
<br /> Process Building superstructure I 25,000 sq.ft. x 135' I mixed 13,375,000 1 cu.ft. 1 $0.18 I $651,240
<br /> I I I I I I
<br /> Administration Building superstructure I 50'L x 30'W x 161H I mixed I 24,000 I cu.ft. 1 $0.18 1 $4,631
<br /> I I I I I I
<br /> Substation superstructure I 30'L x 301W x 101H I mixed I 9,000 I cu.ft. I $0.18 I $1,737
<br /> I I I I I I
<br /> Pump House superstructure I 30'L x 30'W x 181H 1 mixed I 16,200 I cu.ft. I $0.18 I $3,126
<br /> I I I I I I
<br /> Raw water tank I 60' dia. x 481H 1 steel I 135,696 I cu.ft. I $0.18 I $26,184
<br /> I I I I I I
<br /> Cooling Tower I 30'L x 201W x 481H 1 mixed I 28,800 I cu.ft. I $0.18 1 $5,557
<br /> I I I I I t
<br /> Concrete floor, all structures I 12" reinforced I concrete I 31,727 I sq.ft. I $5.52 I $187,743
<br /> I I I I I I
<br /> Concrete footings, equipment pedestals, etc. I 300 c.y. footings, I concrete 1 926 ( cu.yd. I $81.00 I $80,415
<br /> I 626.1 c.y. other l I I I 1
<br /> I I I I I I
<br /> Remove well field piping I 8-12" pipe, 504011, I steel I 5,040 1 lin.ft.1 $8.45 I $45,654
<br /> I I I 1 1 1
<br /> Remove well field piping 1 4" pipe, 342011, 1 steel 1 3,420 1 lin.ft.1 $5.05 1 $18,515
<br /> I I I I I I
<br /> Dispose of well field piping (see notes) 1 see notes I steel I 1*1 lumpsuml **********1 $15,322
<br /> I I I I I I
<br /> Remove and scrap pipe racks (see notes) I see notes I steel 1 1 1 lumpsuml **********I $46,292
<br /> I I I I I I
<br /> Remove pipe rack footings I 1' dia. x 3' I concrete I 90 I cu.yd. I $81.00 1 $7,815
<br /> I I I I I I
<br /> Above ground transmission line I 29,600 linear feet 1 power line I 29,600 1 lin.ft.1 $1.95 1 $61,876
<br /> I I I I I I
<br /> Demolish and remove asphalt from access road I 1.4 mi. x 32' x 4" 1 asphalt I 26,283 I sq.yd I $4.61 I $129,888
<br /> I I I I I I
<br /> Remove fence around facilities area & ponds I n/a I 8' mesh I 4,020 1 lin.ft. 1 $1.70 I $7,326
<br /> I I I I I I
<br /> Cut & fold in liners, double lined ponds I 11 acres I HDPE liner I 11 I acre I $4,000.00 I $47,168
<br /> I I I I I I
<br /> Cut & fold in liner, water storage pond I 10 acres I HDPE.liner I 10 I acre I $2,000.00 I $21,440
<br /> I I I I I I
<br /> TASK SUBTOTAL - sheet 1 $1,361,929