Laserfiche WebLink
• <br />amec <br />Earth & Environmental <br />Summary of Planning Items: <br />Continue placing structural fill within the Phase 5 VLF footprint. <br />Continue processing SLF material at the East Cresson Clay Borrow. <br />Continue processing LVSCF at the Dump 4. <br />Continue receiving geomembrane to site. <br />Continue exposure of the Phase IV geomembrane. <br />Continue subgrade preparation for SLF placement. <br />Continue SLF placement within the Phase 5 VLF footprint. <br />Begin secondary geomembrane installation within the Phase 5 VLF footprint. <br />Summary of Non - conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC& V :: <br />CC &V held a Weekly Construction meeting on May 4, 2010. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />Ames Construction: <br />None <br />• AMEC: <br />Derek Wittwer (Project Manager- 5/4/2010) and Jay Moore (Senior Engineer- 5/6/2010) were on -site to <br />observe /discuss project activities, progress, and scheduling. <br />Others: <br />None <br />Summary of Incidents /Accidents /Health & Safety Issues: <br />None <br />We trust the information provided clearly represents our findings and observations for the week ending <br />May 8, 2010. <br />Joseph D. Hickey, CQA Monitor <br />Approved By: <br />Date: May 8, 2010 <br />Date: <br />VLF Weekly Report WE 05.08.10.D <br />