amecl* <br />C) Cut to Fill <br />1) VLF <br />No work performed during the week. <br />D) Soil Liner Fill <br />1) VLF <br />Soil liner fill (SLF) placement continued in the areas shown on Figure 2. One CAT 385 <br />excavator loaded 40-ton articulating haul trucks from the temporary stockpile location. <br />Subgrade was approved and moisturized prior to placement using a tandem axle water truck. <br />Placement was performed using two CAT D-6 LGP dozers, a CAT D-8 dozer and a CAT skid <br />steer loader in a one-foot compacted lift. Moisture conditioning of SLF material was performed <br />using a tandem axle water truck and compaction was achieved using a 10-ton vibratory smooth <br />drum compactor. Testing will be performed prior to geomembrane deployment in the area. <br />E) High Volume Solution Collection System <br />1) High Volume Solution Collection Piping <br />No placement performed during the week. <br />2) Drain Cover Fill (DCF) <br />No work performed during the week. <br />F) Leak Detection Trench <br />1) VLF <br />No work performed during the week. <br />II) Storm Water Management <br />A) Best Management Practices <br />Best Management Practices are being observed throughout the Phase 5 VLF Project. <br />III) Material Processing <br />A) Drain Cover Fill Process Area <br />No Drain Cover Fill (DCF) was processed during the week. <br />Location This Week Cumulative Comments <br /> (tons) (tons) <br />DCF Process 0 121,223 <br />Total 0 121,223 <br />IV) VLF Geosynthetics <br />A) Geomembrane Installation <br />1) VLF <br />No work performed during the week. <br />VLF Weekly Report WE 06.04.2011