amecs <br />B) Geomembrane Exposure <br />1) VLF <br />Previously installed geomembrane was exposed using a John Deere 35D excavator and <br />laborers between stations E0+00 (+/-) and E4+00 (+/-). The geomembrane was exposed to <br />allow for new geomembrane to be tied in and was observed by an AMEC field representative. <br />C) Anchor Trench <br />1) VLF <br />No work performed during the week. <br />D) Geomembrane Acceptance <br />1) VLF <br />No geomembrane was accepted during the week. <br />E) Geomembrane Delivery <br />1) VLF <br />Two loads (22 rolls) of 80mil LLDPE single sided textured geomembrane rolls were delivered <br />to site during the week. The loads were delivered on a flat bed truck in good condition. The <br />rolls were unloaded using a CAT 950 front-end loader with forks attached. The geomembrane <br />was placed on three pieces of HDPE pipe, stacked two rolls high. An AMEC field <br />representative inventoried the geomembrane and was present at all times during unloading of <br />the geomembrane. <br />CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />AMEC observed slope contouring of the Phase 5 VLF slopes, including hauling excess material to a <br />designated overburden storage area. <br />AMEC observed compaction of subgrade. <br />AMEC observed the excavation and construction of the leak detection trench. <br />AMEC observed the exposure of previously installed geomembrane. <br />AMEC observed and inventoried geomembrane delivered to site. <br />Testing Summary <br />Laboratory testing continued (Particle Size Distribution, Atterberg Limits, Moisture-Density Relations, <br />Specific Gravity, Permeability, and Point Load testing) for sampled materials. <br />VLF Weekly Report WE 05.07.2011