Laserfiche WebLink
bore hole to the lower levels of the mine. Phase II is scheduled to start upon the completion of the <br />underground development evaluation after Phase I. <br />Note: Water table may determine the level that ventilation and rehabilitation can occur. <br />• Re-establish electric, compressed air and water services as required to perform <br />rehabilitation work. <br />• Rehabilitation of approximately 400' of tunnel from the end of Phase I work to the <br />bore hole. Refer to Figure 5 - Phase II. <br />• Rehabilitate the main decline and establish ventilation to the 10,250' and 10,000' <br />levels. Refer to Figure 6 - Phase II. <br />• Establish electric, compressed air and water services to the lowers levels of the <br />workings for a future core drilling program. <br />0 Rehabilitate the ventilation borehole as secondary escape way.