Proposed Decision -North Thompson CreeklPhase II Bond Release <br />November 26, 1993 <br />Page 4 <br />III. CRITERIA FOR BOND RELEASE <br />A permittee is eligible for Phase II Bond Release when the reclaimed area is contributing <br />suspended solids to streamflow or runoff outside the permit area at levels equal to or less <br />than levels found in non-mined areas, according to Rule 3.03.1(3)(b). Up to 85% of the <br />bond may be released upon the successful establishment of the vegetative cover, based <br />on remaining reclamation costs at the site, per Rule 3.03.1(2)(b). <br />The Division reviews topsoil replacement depths, erosion data and the general geo- <br />morphology of the site, as well as vegetative cover and species diversity data when <br />evaluating a Phase II Bond Release request. A bond is calculated which would cover the <br />costs to the Division to bring an independent contractor on site to complete any remaining <br />reclamation. This bond includes a component for vegetation failure. <br />IV. EVALUATION <br />On October 6, 1993, a Phase II Bond Release inspection was performed at the North <br />Thompson Creek Mines. Although the operator originally requested a Phase II Bond <br />Release for both the mine site and the loadout site, only the disturbed prime farmland <br />portion of the loadout site was inspected or considered for Phase II Bond Release for the <br />following reasons: <br />A technical revision (TR-12) to the permit changed the post-mining land use of a portion <br />of the loadout, known as the Diamond A Parcel, from agricultural to residentiallndustrial <br />to allow the construction of a golf course and residential development. The ultimate <br />effect of the TR, which was approved in March 1992, was to allow for removal of the <br />Diamond A Parcel from the mine permit area after the commencement of earth-moving <br />activities for the development. At the time the bond release request was submitted, <br />earth-moving activities at the Diamond A Parcel had not yet begun, so the loadout site <br />was included in the request. The developer, Aspen Glen, has subsequently commenced <br />earth-moving activities. Therefore, the operator has submitted a technical revision to <br />remove the Diamond A Parcel from the permit area concurrently with a final iPhases II and <br />III) bond release request for the Diamond A Parcel. Consequently, the bond release for <br />the Diamond A Parcel will be considered separately from the bond release at the mine <br />site. <br />Larry Routten and Barbara Pavlik led the inspection, and it was attended by Henry Austin, <br />OSM Albuquerque, landowner Robert Perry and his associate Bill Fales, and Jim Stover of <br />MINREC. <br />The first condition which must be met for Phase II Bond Release concerns erosional <br />stability at a site, as defined by Rule 3.03.1(3)(b). A site should not contribute suspended <br />solids to streamflow or runoff outside the permit area in excess of pre-mining levels, as <br />determined by baseline data, or in excess of adjacent undisturbed areas. <br />