<br />I <br />Rule 4.05.4 - Stream Channel Reconstruction <br />12. Response Partially Accepted. Please add the flow direction arrows to the terrace benches <br />on Map 41A as per the map legend. <br />Response. Flow direction arrows have been added to terrace benches on Map 41A as <br />requested. <br />Rule 4.09.2 - Excess Spoil <br />12. Response Partially Accepted. Colowyo has updated all of the typographical errors on <br />page South Taylor/Lower Wilson-Rule 4, Page 20 that were noted in questions a-d. There <br />is, however, a problem with page South Taylor/Lower Wilson-Rule 4, Page 20. Page 20 <br />does not flow correctly from page 19. The end of page 19 and the beginning of page 20 <br />both have Rule 4.06 - Topsoil on them. Please fix either page 19 or page 20. <br />Response: Page 19 has been corrected and provided as requested. <br />New AdegggU Questions Based on Colowyo's 1 Tune 2010 Responses <br />35. Response not accepted. The Division did not ask that small "V's" <br />be added to each contour line where each tributary crosses a contour line. The Division's <br />issue is that Tributary ditches B, D, E, G, and H do not appear to be topographically <br />controlled by the post-mining topography. Further discussion of each problematic <br />tributary is proved as follows. <br />a. Tributary ditch B empties onto the undisturbed area on the side of the ridge and <br />was not present in the pre-mining topography. Please review this tributary ditch <br />and make corrections as necessary. <br />b. Tributary D appears to need moved to the west and the 8050 foot PMT contour <br />should loop back further into the disturbed area. Please revise this tributary ditch <br />and make corrections as necessary. <br />c. Tributary E empties into no apparent existing channel and appears to be <br />unnecessary as no drainage was present in the pre-mining topography. Please <br />review this tributary ditch and make corrections as necessary. <br />d. Tributary G appears to be misaligned based on the post-mining topography and/or <br />may need an additional branch to the west. Please review this tributary ditch and <br />make corrections as necessary. <br />e. Tributary H appears misaligned to the east due to the flat 7900 foot contour bench. <br />Please review this tributary ditch and make corrections as necessary. <br />Response. In Colowyo's previous response, it was stated that all of the channels A though I <br />were sited to route reclaimed area runoff into natural channel segments directly <br />below (downstream of) the PMT tie-in boundary. Pursuant to this more detailed <br />comment No. 35, some ditch alignments on Map 41141A and some of the post- <br />mining topography in this area have been revised. However, the function of the <br />ditches and the intent of the original alignment selection remain unchanged. <br />