Table E-2 Reclamation Timetable <br /> Length of time to <br />Year Phase Comments complete ears <br />2011 1 Site Preparation, Topsoil stripping, build the access road. 0.3 <br /> Mine in Mining Area 1, stockpile topsoil and overburden. Build the <br />2011- 2 containment ditches in the northern portion of the mining areas as 5.6 <br />2017 shown on Map C-2. Seed the stockpile. <br /> Mine in Mining Area 2, stockpile topsoil and place the overburden <br />2017- 3 encountered on the pit floor where available, to the elevation and slopes 3.1 <br />2020 shown on Map F. Seed the stockpiles. <br />2020- 4 Mine in Mining Area 3, create the islands of backfill material to be 3.3 <br />2023 topsoiled as shown on Map F. <br /> <br />2023- 5 Mine in Mining Area 4, place the overburden encountered on the pit 2.7 <br />2026 floor and sideslopes to the elevation and slopes shown on Map F and <br /> direct lace topsoil in Mining Area 3. Seed the reclaimed areas. <br />2026- <br />2030 6 <br />Mine in Mining Area 5,create the finished islands in Mining Area 2,3 4.0 <br /> and 4. Seed all reclaimed areas. <br />2030- 7 Mine in Mining Area 6 while creating a temporary road realingment to 12 <br />2031 the south. create the finished islands in Mining Area 2,3 and 4. Seed all <br /> reclaimed areas <br />2031- Replace the BLM road through Mining Area 6. Replance all stockpiled 0 <br />3 <br />2031 8 Topsoil, remove wash plants and product stockpiles. . <br /> Total 20.2 <br />Craig Ranch Pit, March 2011 E-3