Laserfiche WebLink
8 days X $1200/day $9600 <br />Seed & Fertilizer 1200 <br />Move-in Costs 525 <br />Total Reclamation Cost $11,325 <br />The access roads to and between all pit areas and the power line access <br />roads will remain. <br />Pits 3 and 4: <br />The same 4-man crew and equipment will take 2 days to spread topsoil and <br />fines on the pit slopes. Seeding and dragging or mulching will take another day. <br />3 daysX $1200/day $3600 <br />Seed & Fertilizer 650 <br />Move-in Costs 525 <br />Total Reclamation Costs $4775 <br />Total Reclamation Costs - Pits 1, 2, 3, and 4 <br />Pit 1 $8,575 <br />Pit 2 11,325 <br />Pits 3 & 4 4,775 <br />TOTAL $24,67'5 <br />There is ample equipment in the Town of Silverton, located 3.5 miles south <br />of this site. Most operators in the area will charge $100 - 200 to move in each <br />piece of equipment. <br />A seed mixture as recommended by the NRCS is included and will be used. <br />