amec!ly <br />Earth & Environmental <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: August 29, 2009 <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day <br />Reporting Period: 08/23/09 through 08/29/09 <br />Days S M T W T F S <br />Work Shifts D D D D D - <br /> - N N N N - - <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 437 to 52°F (+/-) High: 76°F to 82°F (+/-) <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: Delays in the processing of clay occurred due to rain early in the week. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />II) EARTHWORKS <br />A) Clearing and Grubbing <br />1) VLF <br />No work performed during the week. <br />B) Stripping <br />1) VLF <br />No work performed during the week. <br />C) Topsoil Relocation <br />1) VLF <br />No work performed during the week. <br />D) Subgrade Preparation <br />1) VLF <br />The final section of area at the Arequa Process area between stations J11+00 (+/-) to J13+00 <br />(+/-), approximately 75 to 150 feet left of centerline, was approved for fill placement. <br />E) Slope Contouring <br />1) VLF <br />Slope contouring was performed between stations H12+00 (+/-) to H16+00 (+/-), <br />approximately 0 to 250 feet right of centerline, H9+00(+/-) to H10+00(+/-), approximately 25- <br />VLF Weekly Report WE 08.29.09.D.doc