Laserfiche WebLink
ame <br />Earth & Environmental <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: 3/21/09 <br />Reporting Period: 03/15/09 through 03/21/09 <br />Days S M T W T F S <br />Work Shifts - D D D D D - <br /> - N N N N N - <br />D = Day Shift N = Night Shift <br />Project No.: 8420125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day <br />Ambient Temperature Range (F): Low: mid 20's to low 30's High: 38° to 50° <br />S <br />In general, the week was relatively mild with moderate winds and mostly clear to partly cloudy afternoon <br />on Friday <br />AMEC CQA Personnel On-site through the Reporting Period (See Attachment A). <br />AMES, No work delays due to weather this week. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />1. EARTHWORKS <br />A. Clear and Grubbing <br />1. VLF <br />Ames continued clearing and grubbing activities below the East Perimeter Access <br />Road. Pioneer roads were used for access. Ames used one to two excavators to <br />consolidate grubbed material for loading. Work has advanced from STA. H6+00(+/-) <br />to STA. H8+00(+/-). Ames used Volvo A40D trucks to transport the material to Pad 4 <br />slash pile located North of Ames maintenance facility. <br />Sediment Collection Pond: <br />Clearing and grubbing has been completed. <br />B. Stripping <br />1. VLF <br />No work this past week. <br />Sheet 1 of 9 VLF Weekly Report WE 03.21.09.13