Laserfiche WebLink
In conjunction with the 6 -North Mains shaft project and extension of the power distribution line, TCC also <br />proposes to construct on the shaft pad a high voltage substation with three power borehole drops, a compressed air <br />station with borehole drop, a rockdust tank station with borehole drop, a bulk material borehole drop and a water <br />• borehole drop for the continued development and mining of the Northern and Western Mine Districts. The <br />boreholes were drilled to a nominal 13 -inch diameter. Water for drilling operations was either trucked -in by tanker <br />or drawn from Fish Creek using a portable pump (under TCC's Boettler Ditch water right — 144 cfs). The cuttings <br />were disposed of in the collection pit. Steel Schedule -40 or -80 pipe was placed in each of the nominal 13 -inch <br />diameter holes, and the annulus was fully grouted. <br />The power distribution component includes construction of the 69 KV powerline, approximate 150 by 150 -foot <br />substation area, switchgear building, grounding bed and three nominal 13 -inch diameter boreholes from the surface <br />to the underground workings at the proposed intake shaft pad above the 6 North Main entries. The substation area <br />consists of powerpoles for powerline termination, transformer pads, and an approximate 14 x 30 -foot prefabricated <br />metal building with foundation, and grounding bed. There are three fuse disconnects and three gang- operated <br />disconnects between the powerpole terminations and the transformers. The metal building houses the switchgear <br />for the power feed from the transformers to the power cables that feed into the power borehole. The grounding bed, <br />located outside of the shaft pad area, consists of copper rods buried in trenches at a depth of approximately 5 feet. <br />In order to hang the power cables in the holes, a steel structure(s) was constructed over the three cased holes. This <br />structure(s) is a metal beam(s) and legs, bolted to a concrete footer(s). The beam(s) will be either 14 feet or 10 feet <br />(up to three) in length, and the legs are approximately 6.5 or 8 feet high. The footer(s) is approximately 4 x 4 x 4 <br />feet. The 14 -foot beam structure extends over all three boreholes. The 10 -foot beam structures will be placed over <br />individual or paired borings, if used. On completion and casing of the borings, a 7 x 10 x 5 -foot pad was poured <br />around the three power -drop boreholes. <br />The rock -dust component includes construction of a 22 x 24 x 1 foot reinforced concrete slab foundation with four <br />2 -foot diameter 9.5 foot reinforced concrete piers, installation of an existing 36 -foot high rock -dust storage tank, <br />00 installation of an electrical power supply for the rock -dust tank and drilling of a nominal 13 -inch borehole from the <br />surface to the underground workings from the shaft pad above the 6 -North Main entries. Drilling of the borehole <br />was covered by the TR05 -48 submittal. The rock -dust tank has a capacity of 2,440 cubic feet, or 100 tons of rock - <br />dust. The tank will deliver rock -dust to the borehole through an air slide angled at 10 degrees. Tank aeration will <br />be provided by the compressor. The tank will be monitored by electronic controls and strain gauges. Electricity <br />will be supplied from the 6 -Main North substation. An electrical line will run from the tank down an existing <br />electrical borehole to controls underground. <br />The air compressor component includes construction of a reinforced concrete slab foundation with stem wall and <br />footer extending 4 -foot below grade, a 30 x 50 x 12 foot compressor building, installation of existing compressors, <br />installation of an electrical power supply for the compressors, installation of Polo Citrus tanks, and drilling of a <br />nominal 13 -inch borehole from the surface to the underground workings from the shaft pad above the 6 -North Main <br />entries. Drilling of the borehole was covered by the TR05 -48 submittal. The compressor building will house two <br />air compressors, two dryers, two 5,000 gallon Polo Citrus tanks, and electrical and control equipment for the <br />systems within the building. The building will be constructed of steel and rest on a designed steel - reinforced <br />concrete foundation. It will be supplied power from the 6 -Main North substation and will be insulated and heated. <br />The Polo Citrus tanks will be enclosed by a containment system capable of holding in excess of 5,000 gallons. <br />The bulk material component includes construction of a pad, installation of a bulk material hopper, and drilling of a <br />nominal 13 -inch borehole from the surface to the underground workings from the shaft pad above the 6 -North Main <br />entries. Drilling of the borehole was covered by the TR05 -48 submittal. Details for the concrete pad and bulk <br />storage and transfer facilities will be submitted for review and approval as a Minor Revision, prior to installation. <br />The water component includes construction of a reinforced concrete pad and footers, installation of a water tank <br />and associated pumping installation, drilling of a nominal 13 -inch borehole from the surface to the underground <br />workings from the shaft pad above the 6 -North Main entries, and construction of the 6MN Mine Water Storage <br />Reservoir. Drilling of the borehole was covered by the TR05 -48 submittal. TCC proposes to construct a steel <br />water tank 85 feet in diameter and 24 feet high designed to hold one million gallons. The tank will rest on a <br />reinforced concrete foundation consisting of a spread- footer, stem wall, and slab floor supported by concrete <br />2.05 — 45.6e 07/28/09 <br />TR06 -57 <br />