Laserfiche WebLink
were used to excavate the shaft. An additional concrete pad(s), nominal size of 40 by 100 feet by 2 feet thick, was <br />placed to accommodate the hoisting winch, transformers, distribution boxes, operator consoles, surrounding <br />building, and other miscellaneous equipment. <br />is Shaft excavation was completed as a progressive cyclic operation, with each excavation cycle consisting of four <br />basic operations; drilling, blasting, mucking, and concrete lining. Drilling involved the use of one or more <br />pneumatic shaft jumbo drills nested in a multiple -deck work stage. Blasting was completed using permissible stick <br />powder and electric detonators. The blasted shaft materials were mucked using in -shaft pneumatic muckers and a <br />nominal 3 -4 yard hoisting bucket. The shaft cuttings were placed by a wheel- loader in a 14 -foot deep, lined <br />temporary mine development waste pit excavated within the shaft pad, adjacent to the shaft excavation, as shown <br />on Maps EX16E -M1 and M2. The cuttings pit is lined with a nominal 30 -mil PVC flexible membrane liner having <br />a permeability of _10 cm/sec. The PVC liner is covered with approximately 6 -8 inches of pit -run material to <br />protect the liner. The shaft concrete lining was placed in nominal 20- to 30 -foot lifts in cycle with the drilling and <br />mucking operation, using a curb -ring and slip -form assembly. During excavation, the shaft work area was <br />ventilated using ventilation ducting and a permissible surface fan. Once the blind sink excavation reached the coal <br />seam, the work stage was removed and disassembled. <br />The cuttings volume generated by shaft sinking operations is approximately 15,126 cubic yards (22,690 cubic yards <br />when swelled by 50 percent, based on 20 -foot diameter and 1,300 -foot depth). If drainage of water from the <br />excavated material resulted in any significant accumulation of water in the cuttings pit, the water was pumped to a <br />water tanker to maintain essentially dry conditions in the pit. Upon completion of the shaft excavation and concrete <br />liner installation, any minor water accumulation in the cuttings pit were allowed to dry -out, and the collection pit <br />and cutting materials were then be covered with previously placed materials from the shaft collar excavation, <br />graded, and revegetated with a temporary cover. A sign(s) was posted designating the temporary mine <br />development waste pit. The cuttings and shaft collar excavation materials will be utilized to re -fill the shaft during <br />eventual reclamation of the facility. <br />The cement liner serves to isolate the Twentymile Sandstone from the Wadge Overburden. As noted above, a pre - <br />grout program is not required in a conventional blind sink. A probe -hole is typically carried down the hole as the <br />shaft is excavated. Water is grouted off from within the excavated shaft as it is encountered. This further assures <br />that, after final closure, the water in this unit is confined and will not seep down on the inside of the shaft. <br />Following completion of shaft excavation and cement lining operations, and removal of equipment from the site, an <br />emergency escape hoist will be installed in the shaft. Hoist installation will involve completion of the following <br />activities, as illustrated by the design information provided in Exhibit 49N, 6MN Emergency Escape Hoist Design <br />Drawings: <br />• Erection of a pre- fabricated steel hoist -frame and bull - wheel, approximately 10 x 22 x 25 feet high over the <br />existing 6MN Ventilation Shaft, tying into the existing concrete shaft collar <br />• Fabrication of a steel frame and expanded metal shaft landing and access stairs, tying into the hoist -frame <br />• Fabrication of a similar shaft landing at the bottom of the shaft <br />• Installation in the shaft of guide -ropes for the hoist cage <br />• Excavation for the hoist -house foundation <br />• Forming and pouring of the 20 x 30 foot reinforced concrete hoist -house foundation <br />• Installation of the hoist motor, winch, and associated control equipment on the hoist -house foundation <br />• Erection of the pre- fabricated steel hoist house <br />• Stringing of hoist cable and placement and connection of the 3 x 5 x 8 foot high pre- fabricated hoist cage <br />• Electrical connections (from existing power distribution line) and testing of hoist <br />• Installation of appropriate equipment guards and fencing <br />Underground Utilities Project Components - Concurrent with road construction, a 69 -KV power distribution line <br />was extended from the existing substation at the Northwest Mains fan location to a pad- mounted transformer at the <br />. 6 North Mains shaft site. The power distribution line is approximately 3,130 feet long with a total of approximately <br />14 powerpoles and is located adjacent to the proposed access road and within the 50 -foot road corridor from road <br />centerline. <br />TR06 -57 2.05 — 45.6d 07/28/09 <br />