May Day and Idaho Mine Complex 112 (d) Permit Application <br />• <br />Table E -1. Approximate time period for mine phases, May Day and Idaho Mine Complex <br />Phase <br />Operation <br />Mine Year <br />1 2 3 14 5 6 <br />7 <br />8 <br />9 <br />1 10 <br />1 <br />Preliminary Activities <br />2 <br />Milling Optimization <br />3 <br />May Day No. 1 Production <br />4 <br />Exploration Activities <br />5 <br />1 Production Expansion <br />6 <br />Milling Completion & Closure <br />6.4.5(2)(e)(ii) Size and location of each area to be reclaimed during each phase <br />As noted in the Mine Plan (Exhibit D), most of the operational activity will occur in underground work- <br />ings. Surface disturbances are limited to the operational areas (depicted on Figure C -4 in Exhibit Q. <br />These individual operational areas are restricted to less than 1.0 acre, and are anticipated to be life of mine <br />and therefore will be reclaimed during final closure. Locations of the facilities and structures detailed <br />below are identified and located in Figure C -4. <br />Phase I - Preliminary Construction and Reclamation Activities <br />• Access Road Construction <br />Primary access road in permit area is immediately off of County Road 124. This road base area is <br />approximately 50 feet wide along a 1,900 foot length (1.76 acres). This road is temporary and <br />will be reclaimed during final reclamation. The road construction work plan is summarized in <br />Attachment 6.5 -3 <br />• Grading of Existing Access Roads <br />Pre - existing access roads within the 20 foot corridor will be graded and reseeded. The 20 foot <br />wide corridor is approximately 8,300 feet in length (4.1 acres). These roads are permanent and <br />will not be reclaimed. <br />• May Day No. 2 Bench - Run of Mine Rock Storage <br />This bench area is approximately 0.8 acre and is within the May Day No. 2 Operational Area. <br />The rock storage site will be designed and reclaimed in accordance with the criteria presented in <br />Exhibit 6.5 <br />• Installation of Stormwater Best Management Practice Structures <br />Stormwater control structures will be installed as outlined in Attachment T -4 located in Section <br />6.4.20(10)(b) of Exhibit T. <br />. • Repair of May Day No. 1 does not require interim reclamation. <br />May Day Idaho Mine Complex 112(d) Permit Application <br />September 21, 2010 <br />14 <br />