Laserfiche WebLink
August 18, 2010 C-1981-041/Roadside Portals MPB <br />SUPPORT FACILITIES - Rule 4.04: <br />Much of the construction work for the Cameo Sand Offloading Facility is completed. Halliburton's contractor <br />FCI was pouring the surface of the new bridge that crosses the lower end of Coal Creek. They were also painting <br />the sand storage silos with a secondary color to aid in screening the tall silos. The UTL 1 and 2 reclaimed pond <br />locations looked very stable. The only problem noted at the UTL was that the large silt fence that protects the <br />wetland area located southwest of the former UTL land 2 Ponds has been damaged by the significant rainstorm <br />that occurred in the area prior to this inspection. The silt fence appears to have functioned properly by retaining <br />sediment from entering the wetland area but has been damaged from the recent storm as shown in attached <br />Photograph No's 5 and 6. Please repair and replace as needed all damaged silt fence structures in the UTL loop <br />area prior to the SL-7 bond release scheduled for September 23, 2010. <br />Number of Partial Inspection this Fiscal Year: 1 <br />Number of Complete Inspections this Fiscal Year: 1 <br />Page 4 of 9