(Page 3) <br />MINE ID # OR PROSPECTING ID #: M-1975-009 <br />INSPECTION DATE: 22 J1 Iv 2010 INSPECTOR'S INITIALS: DB2_ <br />The following problems (PB) and/or possible violations (PV) (and suggested corrective actions) were identified during this <br />inspection. The problems should be corrected by the dates given, or they will become possible violations. The possible <br />violations should be corrected by the dates given to reduce their severity when considered by the Mined Land Reclamation <br />Board. The inspector noted on the previous page should be notified of all corrective actions taken. <br />PROBLEMS/POSSIBLE VIOLATIONS <br />AND <br />CORRECTIVE ACTIONS <br />CORRECTION DATE <br />1 / Problem: The sign at the mine entrance, as required by Rule 3.1.2 (1), is missing 10/ 08/2010 <br />PB or PV: PB <br />TOPIC(S): --5h1 <br />Corrective Action: Within 60 days from the date of mailing of this inspection report osp t the <br />required sign at the entrance to the mine site. The sign must be clearly visible from the access road 7W <br />and must contain all of the required wording specified in Rule 3.1.12 (1). <br />J2. Problem: The records on file with the Division are not adequate to locate the permitted area on 11/08/2010 <br />the ground. <br />PB or PV: PB <br />TOPIC(S): A-L <br />Corrective Action: Within 90 days from the date of mailing of this inspection report. submit a <br />r vice n that accurately depicts the permit boUndarv. Or alternatively, the operator may submit <br />a Technical Revision that modifies the permit boundary by consolidating the permit into one parcel <br />around the southern excavation and releasing the two northern parcels from the permit. <br />3.? Problem: The financial warranty is not at a level that reflects the actual cost to reclaim the site. /FBD/ <br />PB or PV: PB <br />TOPIC(S): FW <br />Corrective Action: Provide additional financial warranty sufficient to bring the total financial <br />warranty up to $8.385. Official notification of the increase will be sent under separate cover. and the <br />operator will 60 days from the date of that letter to provide the additional amount. <br />A <br />have