Bowie No. 2 Mine C- 1996 -083 <br />Task 165 - Structural Demolition <br />Task: 165 <br />Site: Bowie No. 2 Mine <br />Date: 26- Jan -10 <br />User: JRS <br />Permit Action: <br />2009 Midterm Review <br />County <br />Delta <br />Description: <br />Demolish and Remove All Structures <br />File Name: <br />C -1996 -083 <br />Description <br />Reference <br />Quantity <br />Unit Cost <br />Total Cost <br />Clean Material Storage Areas <br />$ - <br />- Gob Pile <br />968 <br />CY <br />$13.3500 <br />$ 12,922.80 <br />- Haul Road Piles (2) <br />484 <br />CY <br />$13.3500 <br />$ 6,461.40 <br />- Topsoil Stockpile A <br />1,839 <br />CY <br />$13.3500 <br />$ 24,550.65 <br />- Portal Bench/Light -Use Road (2) <br />1,670 <br />CY <br />$13.3500 <br />$ 22,294.50 <br />PORTAL LEVEL CONVEYOR AND RECLAIM <br />Portal Conveyor <br />140 <br />LF <br />$41.3100 <br />$ 5,783.40 <br />- Footing <br />5 <br />LF <br />$20.5900 <br />$ 102.95 <br />Gob Belt <br />81 <br />LF <br />$41.3100 <br />$ 3,346.11 <br />- Footing <br />2 <br />LF <br />$20.5900 <br />$ 41.18 <br />Stockpile Conveyor <br />393 <br />LF <br />$41.3100 <br />$ 16,234.83 <br />- Footing <br />16 <br />LF <br />$20.5900 <br />$ 329.44 <br />Reclaim Conveyor <br />402 <br />LF <br />$41.3100 <br />$ 16,606.62 <br />- Footing <br />18 <br />LF <br />$20.5900 <br />$ 370.62 <br />Off -Spec Coal Conveyor <br />111 <br />LF <br />$41.3100 <br />$ 4,585.41 <br />- Footing <br />4 <br />LF <br />$20.5900 <br />$ 82.36 <br />Collecting Conveyor <br />76 <br />LF <br />$41.3100 <br />$ 3,139.56 <br />- Footing <br />2 <br />LF <br />$20.5900 <br />$ 41.18 <br />Radial Stacker #1 <br />150 <br />LF <br />$41.3100 <br />$ 6,196.50 <br />- Footing <br />6 <br />LF <br />$20.5900 <br />$ 123.54 <br />Radial Stacker #2 <br />80 <br />LF <br />$41.3100 <br />$ 3,304.80 <br />- Footing <br />1 <br />LF <br />$20.5900 <br />$ 20.59 <br />Stoker Collecting <br />29 <br />LF <br />$41.3100 <br />$ 1,197.99 <br />- Footing <br />2 <br />LF <br />$20.5900 <br />$ 41.18 <br />Stacking Tube (18" Thick) <br />3,204 <br />CF <br />$0.2257 <br />$ 723.14 <br />- Structure <br />8,000 <br />SF <br />$0.2257 <br />$ 1,805.60 <br />- Footing <br />200 <br />LF <br />$10.2900 <br />$ 2,058.00 <br />Reclaim Tunnel Part 1 <br />9,065 <br />SF <br />$7.7700 <br />$ 70,435.05 <br />Reclaim Tunnel Part 2 <br />1,481 <br />SF <br />$7.7700 <br />$ 11,507.37 <br />Page 3 of 12 <br />