Laserfiche WebLink
Change Orders <br />Change Order #1: May 26, 2000 <br />1) Additional machine time could be used to further regrade the access road and other <br />locations to approximate original contours. Bond monies were available and the Coal <br />Program approved of the additional reclamation. An estimated 40 hours of track -hoe time <br />@ $75 /hr was directed for an additional $3,000. The item extended the contract 5 days. <br />2) Additional regrading required additional revegetation work. Approximately 2 acres of <br />additional revegetation was needed. The Additive Alternate #4, Revegetation, amount of <br />$500 was applied. This item extended the contract 1 day. <br />3) Excessive winds and inclimate weather for revegetation were experienced extending the <br />contract an additional 5 days. <br />The total Change Order costs resulted in an increase to the Purchase Order of $3,500. <br />IV. CONSTRUCTION SUMMARY <br />Construction start-up was delayed because of tardiness in State Purchasing issuing the contract. <br />Prior to issuing the Notice to Proceed, the contractor had already mobilized a Komatsu D41 E <br />dozer to the site and had also installed a locking gate at the start of the access road to the bench <br />to prevent vandalism of the machinery. A Komatsu PC200 track -hoe and a MOXY MT30 Rock <br />truck were mobilized on —site and were used for moving the excavated channel material initially <br />against the trench side cuts and eventually to the designated disposal area to the south. At the <br />later part of slope reduction, material moved to the designated disposal area from the base was <br />performed by the rock truck and a Komatsu WA380 tire loader. The amount of rock encountered <br />during channel excavation was more than sufficient to satisfy the riprap requirements. An excess <br />amount of greater than 4'd rock was encountered. The larger rock was. approved for channel <br />placement as long as it was keyed in per specs. Rock placement in the channel was exciting <br />watching the loader dumping rocks at the top of the channel and watching the hoe trying to <br />defend itself from damage. <br />Field Directive #1 was issued shortly after construction commenced. An argument was brought up <br />by the contractor regarding the specifications which referred to two given elevation points and how <br />the slope between them could not be changed from the original /pre - construction grade. Field <br />Directive #1 stated: "There was an oversight on document preparation which neglected to state, in <br />writing, that the channel from the lower point of the gully headcut would) be constructed at a 3:1 on <br />Drawing #1 referenced for final grade. The `construct 3:1 channel from lower (point gully headcut) <br />to bottom of fill slope per specs' referenced 2 given elevation points that exhibited a 2.5:1 and <br />cannot be graded to a 3:1. Therefore the lower point (gully headcut) to bottom of fill slope grade <br />will be at a 2.5:1 per pre- construction ". Concern was made by the Coal Program as to the area <br />where the slope would transition between the 3:1 and the 2.5:1. Previous experience has shown <br />how slope transition areas are subjected to higher erodibility from flow velocity and that the <br />transition zone should located higher up -slope as possible. <br />Field Directive #2 authorized additional machine time, Additive Alternate #1 (track -hoe), to be <br />used for additional side channel work from the east and at the toe of the slope. It also directed <br />that machine time could be used to pull out the drainage to the west, to start the access road <br />recontouring, and for sediment pond spillway work. Field Directive #2 also allowed for diviting with <br />the hoe bucket as being an acceptable surface roughening instead of the specified dozer blade <br />furrowing. <br />