14.0 Construction Schedule <br />Construction of the proposed ore storage pad will occur following approval of the <br />design from DRMS and prior to ore production. Surface preparation at the ore storage <br />pad area will be completed, followed by the installation of the PVC geomembrane, <br />then backfill. Denison will notify DBMS in writing 10 working days prior to <br />construction so that a pre-construction inspection can be conducted and, if need be, <br />construction oversight scheduled. It is anticipated that the construction timeframe to <br />complete the ore storage pad will be less than two months upon commencement of <br />these activities. Following construction of the ore pad, Denison will provide DRMS <br />with certification by a professional engineer or other appropriately qualified <br />professional that will confirm that the facility has been constructed in accordance with <br />the approved design plan. <br />• <br />• <br />14-1 <br />T:\64986-1)enison Mines\Task Order 4 - EPP Sunday Mines Group-Van4\Van40RMS RTC and Revised EPPT INAL DRMS Report - EPP Van4.doc