Laserfiche WebLink
October 2004 -9- 043 -2170 <br />approximately 10 feet below the finished surface grade. The surfacc of the CSB <br />40 was compacted using the shovel from a CAT 330b excavator. A 3 -foot minimum <br />CP was cast into the shaft and allowed to cure for a minimum of 7 days. A <br />minimum 7 -foot thick layer of CR was then placed onto the CP. SF was then <br />placed to the final grade, as needed. In some cases, the excavation did not require <br />placement of CSB prior to placement of the CP and CR. <br />For open workings where the depth to competent bedrock was greater than 7 feet to <br />the final SLF subgrade surface, the excavations were backfilled with CSB to 3 feet <br />below the soil/bedrock interface. The surface of the CSB was compacted using the <br />shovel from a CAT 330b excavator. A 3 -foot minimum CP was cast into the shaft <br />and allowed to cure for a minimum of 7 days. A minimum Moot thick layer of CR <br />was then placed onto the CP. After the CR was allowed to cure, SF was then placed <br />to the final grade, as needed. In some cases, the excavation did not require <br />placement of CSB prior to placement of the CP and CR. <br />• For collapsed workings extending deeper than 25 feet and where the depth to <br />competent bedrock was less than 7 feet to the final SLF subgrade surface, the <br />collapsed materials were excavated to a depth of 25 feet below finished grade. The <br />excavations were either backfilled with CSB to approximately 10 feet below the <br />finished grade or shaped for the CP at a workable depth below 10 feet. The surface <br />of the CSB or existing material was compacted using the shovel from a CAT 330b <br />excavator. A 3 -foot minimum CP was cast into the shaft and allowed to cure for a <br />minimum of 7 days. A minimum 7 -foot thick layer of CR was then placed onto the <br />CP. After the CR was allowed to cure, SF was then placed to the final grade, as <br />• needed. In some cases, the excavation did not require placement of CSB prior to <br />placement of the CP and CR. <br />For collapsed workings extending deeper than 25 feet and where the depth to <br />competent bedrock was greater than 7 feet to the final SLF subgrade surface, the <br />collapsed materials were excavated to a depth of 25 feet below finished grade. The <br />excavations were either backfilled with CSB to approximately 3 feet below the <br />soil/bedrock interface or shaped for placement of the CP. The surface of the CSB <br />was compacted using the shovel from a CAT 330b excavator. A Moot minimum <br />CP was cast into the shaft and allowed to cure for a minimum of 7 days. A <br />minimum 7 -foot thick layer of CR was then placed onto the CP. After the CR was <br />allowed to cure, SF was then placed to the final grade, as needed. <br />Shallow surface pits that were less than 25 feet deep below the final SLF subgrade <br />surface were excavated to bedrock or pit termination. The pits were then backfilled <br />with compacted SSF and SF to the final subgrade elevation. <br />In some cases, shallow surface pits were completely removed during slope re- <br />contouring and required no further remediation. <br />• <br />L-%ftM 4W, CeK .Qerervamaia3ximNM124KCgnPkIVGdm Golder Associates <br />