~- <br />TABLE 3.7 - 2 RECLAMATION TIMETABLE <br /> <br />~` <br />Scheduled Scheduled Reclaimed <br />PROJECT Start Completion Area <br />YR & QTR YR & QTR ACRES <br />Phase 1 Phase 2 <br />Earthwork <br />Haul Road 3Q - 2016 4Q - 2016 1.5 <br />McClave to Munger Road 3Q • 2016 4Q - 2016 <br />Bench Area 2Q - 2016 4Q • 2016 2.9 <br />Office & Parking Lot 3Q • 2016 4Q • 2016 0.9 <br />Rip-rap Stockpile 3Q - 2016 4Q - 2016 0.1 <br />Bridge 3Q - 2016 4Q - 2016 <br />Topsoil Stockpile 3Q - 2016 4Q • 2016 0.2 <br /> Sediment Pond 3Q • 2018 4Q • 2018 <br /> Sediment Traps 3Q • 2018 4Q • 2018 <br />Facilities <br />Trailer Removal 2Q • 2016 2Q - 2016 N/A <br />Foundation Removal 2Q - 2016 3Q - 2016 N/A <br />Remove Portable Equipment 2Q • 2016 3Q • 2016 N/A <br />Portal Seals 2Q • 2016 2Q • 2016 N/A <br />Mine Water Tanks 2Q • 2016 2Q - 2016 N/A <br />Office Water Tanks 2Q • 2016 2Q - 2016 N/A <br />Fuel Tanks 2Q - 2016 2Q • 2016 N/A <br />Seeding <br />Bench Area 4Q - 2016 4Q - 2016 2.9 <br />All Roads 4Q • 2016 4Q • 2016 <br />Office & Parking Lot 4Q • 2016 4Q - 2016 0.9 <br />Topsoil Stockpile 4Q • 2016 4Q - 2016 <br /> Sediment Pond 4Q • 2018 4Q • 2018 <br /> Sediment Traps 4Q • 2018 4Q • 2018 <br />Mc <br />Volume 1 <br />4-29-96 <br />