amec <br />Earth 8 Environmental <br />H) Material Processing <br />1) South Cresson Clay Processing Area <br />Processing of Soil Liner Fill material resumed at the South Cresson Clay Process. A CAT D-6 <br />dozer, a CAT 330 excavator, and a CAT 966 front-end loader were used to process the <br />material. <br />Location This Week <br />tons Cumulative Comments <br />So Cresson Clay Processing 9,005 93,553 <br />Squaw Gulch Processing 0 35,816 Processing in area complete. <br />Total 9,005 129,369 <br />I) New ADR Water Tank and Waterline <br />New Crusher waterline trench excavation continued using a CAT 330 excavator. Pipe bedding and <br />HDPE pipe were placed in the trench using a CAT 966 front-end loader. <br />J) Miscellaneous <br />Removal of the old solution lines continued by cutting the welds in the lines using an <br />oxy/acetylene cutting torch. <br />III) Underground Workings <br />A) Drilling <br />No work performed during the week. <br />B) Mine Shaft/Stope Remediation <br />No work performed during the week. <br />C) Lateral/Slot Remediation <br />No work performed during the week. <br />IV) Storm Water Management Structures <br />A) Control Structures <br />No work performed during the week. <br />B) Best Management Practices <br />Best Management Practices are being observed throughout the VLF Phase 5 Project. Storm water <br />controls were maintained throughout the week. Precipitation was not substantial during the week. <br />V) VLF Geosynthetics <br />No work performed during the week. <br />CQA ACTIVITIES: <br />SUMMARY: <br />The CQA activities performed consisted of observing, documenting and recording the construction <br />activities of the contractor. <br />VLF Weekly Report WE 10.03.09.D.doc