ameO <br />Earth & Environmental <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day <br />Work Element: Phase 5 CQA/ VLF <br />Date: September 26, 2009 <br />Reporting Period: 09/20/09 through 09/26/09 <br />Days S M T W T F S <br />Work Shifts D D D D D - <br /> - N N N N N - <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 24°F to 42°F (+/-) High: 37°F to 69°F (+/-) <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: Work activities were suspended on Monday (9/21/2009) at approximately 1 I:00am due to heavy <br />snow and slick haul routes. Haulage was resumed Tuesday (9/22/2009) at approximately <br />10:00am. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />II) EARTHWORKS <br />A) Clearing and Grubbing <br />1) VLF <br />No work performed during the week. <br />B) Stripping <br />1) VLF <br />No work performed during the week. <br />C) Topsoil Relocation <br />1) VLF <br />No work performed during the week. <br />D) Subgrade Preparation <br />1) VLF <br />Subgrade preparation was performed in the following areas: between stations A0+50 (+/-); <br />A2+25 (+/-); E19+00 (+/-); and E23+00 (+/-), approximately 0 to 200 feet left of "E" <br />centerline; and between stations J1+00 (+/-) and J13+00 (+/-), approximately 50 to 200 right of <br />centerline. A CAT D-9 dozer and a CAT D-6 dozer were used to rip the subgrade surface to a <br />depth of 6" to 8". The subgrade was then moisture conditioned using a CAT 773 water tuck <br />VLF Weekly Report WE 09.26.09.D.doc