Demolition Work
<br />Page 1 of 6
<br />Prolect Identification
<br /> Agency or organization name: o Division of Reclamation, Mining and Safety
<br />Task #: 001 Permit/job#: C-80-007
<br />Date: 4282009 Abbreviation: N/A
<br />User: TAK Site: West Elk Mine Filename:
<br />ting action: Midterm Review 6 (2009) Source of unit costs: CIRCES
<br />lescription: Demolish and remove all structures in Main Surface Facilities area Location adjustment: 92.32%
<br /> Last unit cost update: 7/1/2007
<br />STRUCTURE or ITEM DESCRIPTION QUANTITY UNIT CIRCES DEMO. MENU SELECTION UNIT COST TOTAL COST % LIAB. TOTAL
<br /> ft It ft If in (100%LIAB.) (ACTUAL)
<br />Warehouse
<br />Superstructure 60 60 28 134,400 CF Demo/disp./exc. pit- 1OK' haul $0.19 $25,401.60 100% $25,401.60
<br />Floor 80 60 8 4,800 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.68 $12,864.00 100% $12,864.00
<br />Footings 1 2 280 280 LF Demo/disp./exc. pit, 1'X2' - 200 ft. $8.03 $2,248.40 100% $2,248.40
<br />Warehouse/office addition
<br />Superstructure 80 18 12 17,280 CF Demo/disp./exc. pit- 10K' haul $0.19 100%
<br />Floor 80 18 10 1,440 SF Demo.disp exc. pit, 10" th. - 200 ft. $3.35 $4,824.00 100% $4,824.00
<br />Footings 1.5 2 38 38 LF Demo/disp./exc. pit, 1.5'X2' - 200 ft. $12.04 $457.52 100% $457.52
<br />Three-sided warehouse
<br />Superstructure 125 25 15 46,875 CF Demo/disp./exc. pit- 10K' haul $0.19 $8,859.38 100% $8,859.38
<br />Floor 125 25 18 3,125 SF Concr., demo. only, rod reinf., 12" th. $10.62 $33,187.50 100% $33,187.50
<br />Footings 1 2 300 600 LF Demo/disp./exc. pit, 1'X2' - 200 ft. $8.03 $4,818.00 100% $4,818.00
<br />Office and bathhouse
<br />Superstructure 122 115 28 392,840 CF Demo/disp./exc. pit - 10K' haul $0.19 $74,246.76 100% $74,246.76
<br />Floor 122 115 6 14,030 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.01 $28,200.30 100% $28,200.30
<br />Footings 2 3 434 434 LF Demo/disp./exc. pit, 2'X3'- 200 ft. $24.08 $10,450.72 100% $10,450.72
<br />Garage
<br />Superstructure 57 33 14 26,334 CF Demo/disp./exc. pit - 1OK' haul $0.19 $4,977.13 100% $4,977.13
<br />Floor 57 33 1,881 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.01 $3,780.81 100% $3,780.81
<br />Loading/unloading dock
<br />Floor 50 10 8 500 SF Concr., demo. only, rod reinf., 8" th. $5.98 $2,990.00 100% $2,990.00
<br />Walls 20 18 8 360 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.68 $964.80 100% $964.80
<br />Bulk fuel storage building
<br />Superstructure 73 39 23 65,481 CF Demo/disp./exc. pit - 1OK' haul $0.22 $14,274.86 100% $14,274.86
<br />Floor 73 39 15 2,847 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.01 $5,722.47 100% $5,722.47
<br />Containment wall 10 437 6 4,370 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.21 $9,657.70 100% $9,657.70
<br />Maintenance shop
<br />Superstructure 181 61 30 331,230 CF Demo/disp./exc. pit- 1OK' haul $0.19 $62,602.47 100% $62,602.47
<br />Stem walls 464 8 8 3,712 SF Demo.disp exc. pit, 8" th. - 200 ft. $2.94 $10,913.28 100% $10,913.28
<br />Footings 3 2 316 316 LF Demo/disp./exc. pit, 2'X3- 200 ft. $24.08 $7,609.28 100% $7,609.28
<br />Barrel storage yard
<br />Floor 25 25 6 625 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.01 $1,256.25 100% $1,256.25
<br />Walls 75 0.5 6 38 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.21 $82.88 100% $82.88
<br />Fence 75 75 LF Fencing, chain link - 8 to 10 ft. high $2.25 $168.75 100% $168.75
<br />Heated storage
<br />Walls 56 0.67 6 38 SF Demo.disp exc. pit, 6" th. - 200 ft. $2.21 $82.92 100% $82.92
<br />Rock dust bin
<br />Superstructure 20 16 12 3,840 CF Demo/disp./exc. pit - 1 OK' haul $0.19 $725.76 100% $725.76
<br />Floor 20 16 4 320 SF Demo.disp exc. pit, 4" th. - 200 ft. $1.34 $426.80 100% $428.80
<br />Footings 1 2 96 96 LF Demo/disp./exc. pit, 1'X2' - 200 ft. $8.03 $770.88 100% $770.88
<br />Rock dust bin
<br />Superstructure 12 18 10 2,160 CF Demo/disp./exc. pit- 10K' haul $0.22 $470.86 100% $470.88
<br />Floor 12 8 4 96 SF Demo.disp exc. pit, 6" th. - 50 ft. $1.99 $191.04 100% $191.04
<br />Footings 1 2 96 96 LF Demo/disp./exc. pit, 1'X2'- 200 ft. $8.03 $770.88 100% $770.88
<br />Water treatment plant 100%
<br />Superstructure 30 24 16 11,520 CF Demo/disp./exc. pit- 10K' haul $0.19 $2,177.28 100% $2,177.28
<br />Floor 36 24 6 864 SF Concr., demo. only, ave. reinf., 6" th. $1.93 $1,667.52 100% $1,667.52
<br />Footings 2 3 34 34 LF Demo/disp./exc. pit, 2'X3'- 200 ft. $24.08 $818.72 100% $818.72
<br />Water intake building
<br />Superstructure 14 14 12 2,352 CF Demo/disp./exc. pit - 10,000' haul $0.17 $409.25 100% $409.25
<br />Floor 14 14 6 196 SF Concr., demo. only, no reinf., 4" th. $2.69 $527.24 100% $527.24
<br />Footings 1 2 56 56 LF Demo/disp./exc. pit, 1'X2'- 200 ft. $8.03 $449.68 100% $449.68
<br /> Tota l for this page before location adjustment $340,049.69
<br /> Location adjustment: 92.32% Total for this page after location adjustment $313,933.87
|