AWN, <br />amle <br />Earth & Environmental <br />3) Topsoil Relocation <br />One John Deere 850 excavator was loading CAT 777 haul trucks with topsoil. Topsoil was <br />transported to the designated topsoil stockpile adjacent to the LOB Delivery Road. One CAT <br />D-9 was assisting the excavator. <br />C) Overburden to Stockpile: <br />1) VLF <br />Oversize rock within in the VLF fill area was stockpiled using a CAT D-9 dozer for future haul <br />to the Joe Dandy Main Cresson Backfill. <br />Rockbreakers: Shot hole drilling was completed between stations A17+50 (+/-) to A20+00(+/-) <br />using four Tamrock track mounted drill rigs. The shots were fired on Thursday and Friday. <br />2) VLF Subgrade Preparation <br />Subgrade preparation was performed between stations A43+00 (+/-) and A47+50 (+/-), <br />approximately 100 to 350-feet left of centerline. The site encompasses an area approximately <br />350 feet in length and approximately 75 to 100 feet in width. <br />Subgrade preparation was performed between stations A24+50 (+/-) and A26+00 (+/-), <br />A27+50 (+/-) and A30+50 (+/-), A36+00 (+/-) and A39+00 (+/-), approximately 75-feet right <br />of centerline. The site encompasses a total area of approximately 750-feet in length and <br />approximately 75-feet in width. <br />Subgrade preparation was performed between stations A20+00 (+/-) and A23+50 (+/-), <br />approximately 75 to 100-feet left of centerline. The site encompasses an area of approximately <br />300 to 350-feet in length and 125-feet wide. <br />All unsuitable material from the sites was loaded using one CAT 375 excavator and <br />transported using articulating 40-Ton haul trucks to a designated site within the mine property. <br />The sites were scarified to a depth of 12 to18-inches using a CAT D-10 dozer and moisture <br />conditioned using a CAT 773-water truck. <br />3) VLF, PSSA Haul Road <br />No work performed during the week. <br />D) Cut to Fill <br />1) VLF <br />Structural Fill was excavated from the LOB Delivery Road cut from stations 1+00 (+/-) to <br />3+00 (+/-), and the proposed water storage tank location. Structural fill was placed on the VLF <br />between stations K2+50 (+/-) and K9+00 (+/-), 0 to 100 feet right of the shoulder of the PSSA <br />Haul Road using available CAT 777 and 40-Ton articulating haul trucks. Structural Fill was <br />placed using one CAT D-8 dozer. Lift thickness was 18 to 24-inches (based on rock size). <br />Field observations indicated there was greater than 30% rock retained on the 3/4 -inch sieve. <br />Moisture conditioning of the fill was performed using a CAT 773-water truck. Each lift was <br />compacted with a smooth drum vibratory roller a minimum of four passes over the entire <br />surface (method compaction technique is applicable). Ambient temperatures were observed <br />during fill placement. <br />Sheet 2 of 6 <br />VLF Weekly Report WE 05.23.09.D