amec <br />Earth & Environmental <br />Structural fill from the LOB Delivery Road cut will continue to be used for the LOB Pad fill and LOB <br />Delivery road fill. <br />At the LOB Pad, the planned MSE Wall to start next week <br />Backfill for the Transfer Station #5 retaining wall is scheduled to start next week. <br />Remediation work to start next week on underground workings 2036 and 2040. <br />Continue site grading in the Conveyor 4 Corridor. <br />Summary of Non-conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC& V. <br />CC&V held a Weekly Construction meeting on May 12, 2009. Items discussed included Safety, <br />Environmental, Schedule, QC documentation, and CQA. <br />Ames Construction: <br />Daily Safety/Tailgate Meetings: AMEC personnel attended the Ames daily safety meeting held at <br />6:40AM prior to the start of shift. Discussions centered on safety and planned work activities. <br />AMEC: <br />Derek Witter, P.E. is updated regularly on the progress of construction and CQA activities and addresses <br />any issues that arise. <br />John Lupo, P E. was notified of the underground working 2030 exposed in the LOB Delivery Road. <br />Others: <br />None <br />Summary of Incidents/Accidents/Health & Safety Issues <br />None <br />We trust the information provided clearly represents our findings and observations for the week ending <br />May 16, 2009. <br /> <br />Date: May 16, 2009 <br />Stephen G. Rice, CQA Monitor <br />Approved By: <br />Date: sle;/ _ <br />Sheet 4 of 8 <br />LOB Weekly Report WE 05.16.09.D.doe