<br />amec <br />Earth 8 Environmental <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: August 15, 2009 <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day <br />Reporting Period: 08/09/09 through 08/15/09 <br />Days S M T W T F S <br />Work Shifts - D D D D D - <br /> - N N N N - - <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 47°F to 53°F (+/-) High: 65°F to 82°F (+/-) <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: No delays due to weather. Night shift resumed Monday, 8/10/2009. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />II) EARTHWORKS <br />A) Clearing and Grubbing <br />1) VLF <br />Tree removal from the east slope of the Phase 5 VLF footprint continued using a CAT 375 <br />excavator and 40-ton articulating haul trucks. The removed trees and slash were placed in the <br />Dump 4 slash stockpile. <br />B) Stripping <br />1) VLF <br />No work performed during the week. <br />C) Topsoil Relocation <br />1) VLF <br />No work performed during the week. <br />D) Subgrade Preparation <br />1) VLF <br />No work performed during the week. <br />VLF Weekly Report WE 08.15.09.D.doc