amec <br />Earth S Environmental <br />vibratory smooth drum compactor, passing over the entire fill surface at least 4 times (method <br />compaction technique is applicable). <br />Structural fill placement was performed between stations J15+00 (+/-) and J17+00 (+/-), <br />approximately 75 feet left of centerline to 75 feet right of centerline. The material pushed from <br />the cut area between stations J 15+00 (+/-) and J 17+00 (+/-), approximately 75 feet left of <br />centerline to 75 right of centerline. The structural fill material was spread in 18" to 24" lifts <br />using a CAT D-8 dozer. Each lift was moisture conditioned using a CAT 773 water truck <br />(when necessary) and compacted using a 10-ton vibratory smooth drum compactor, passing <br />over the entire fill surface at least 4 times (method compaction technique is applicable). <br />Blast pattern drilling was performed by Rockbreakers in the following areas: between A7+00 <br />(+/-) and A8+50 (+/-), approximately 0 to 40 feet left of centerline; between stations A10+00 <br />(+/-) and A10+75 (+/-), approximately 0 to 20 feet left of centerline; and between stations <br />A17+50 (+/-) and A18+00, approximately 15 to 30 feet left of centerline using three to four <br />track mounted drill rigs. Drill pattern blasting was performed on Monday (8/3/2009), Tuesday <br />(8/4/2009), and Friday (8/7/2009). <br />G) Material Processing <br />1) South Cresson Clay Processing Area <br />Processing of Soil Liner Fill material continued at the South Cresson Clay Processing area. A <br />CAT D-6 dozer, a CAT 330 excavator, and a CAT 966 front-end loader were used to process <br />the material. <br />Location This Week <br />tons Cumulative <br />tons Comments <br />So Cresson Clay Processing 5,866 59,083 <br />Squaw Gulch Processing 0 35,816 Processing in area complete. <br />Total 5,866 94,899 <br />H) New ADR Water Tank <br />Manhole and piping construction continued at the new ADR water tank. <br />I) Miscellaneous <br />The headwall for the 84" culvert near station E22+00 (+/-) was removed using a CAT 345 <br />excavator. <br />III) Underground Workings <br />A) Drilling <br />No work performed during the week. <br />B) Mine Shaft/Stope Remediation <br />No work performed during the week. <br />C) Lateral/Slot Remediation <br />No work performed during the week. <br />VLF Weekly Report WE 08.08.09.D.doc