amec*O <br />Earth & Environmental <br />D) Subgrade Preparation <br />1) VLF <br />No work performed during the week. <br />E) Cut to Fill <br />1) VLF <br />A John Deere 850D excavator, a Komatsu 800 excavator, a CAT 375 excavator, and a CAT <br />385 track excavator excavated structural fill material from the following areas: between <br />stations J20+00 (+/-) and J23+00 (+/-), approximately 0 to 100 feet left of centerline; between <br />stations H24+00 (+/-) and H31+50 (+/-), approximately 0 to 75 feet right of centerline; <br />between stations A8+50 (+/-) and A13+00 (+/-), approximately 40 left of centerline to 40 feet <br />right of centerline; between stations A25+00 (+/-) and A26+00 (+/-), approximately 25 feet left <br />of centerline to 100 feet right of centerline; and between A44+00 (+/-) and A46+00 (+/-), <br />approximately 0 to 30 feet left of centerline. The structural fill material was transported using <br />777 haul trucks and 40-ton articulating haul trucks. <br />Structural fill was placed between stations A36+00 (+/-) and A38+00 (+/-), approximately 30 <br />feet right of centerline to 75 feet left of centerline. Structural fill was placed using CAT dozers <br />in 18" to 24" lifts (based on rock size). Moisture conditioning of the fill was performed using a <br />CAT 773-water truck. Each lift was compacted with a 10-ton smooth drum vibratory <br />compactor passing over the entire surface at least 4 times (method compaction technique is <br />applicable). <br />Structural fill was placed between stations A45+00 (+/-) and A48+00 (+/-), approximately 200 <br />to 400 feet left of centerline. Structural fill was placed using CAT dozers in 18" to 24" lifts <br />(based on rock size). Moisture conditioning of the fill was performed using a CAT 773-water <br />truck. Each lift was compacted with a 10-ton smooth drum vibratory compactor passing over <br />the entire surface at least 4 times (method compaction technique is applicable). <br />Structural fill was placed between stations K8+00 (+/-) and K13+00 (+/-), approximately 40 <br />right of centerline to 150 feet left of centerline. Structural fill was placed using CAT dozers in <br />18" to 24" lifts (based on rock size). Moisture conditioning of the fill was performed using a <br />CAT 773-water truck. Each lift was compacted with a 10-ton smooth drum vibratory <br />compactor passing over the entire surface at least 4 times (method compaction technique is <br />applicable). <br />Structural fill was placed between stations F 10+50 (+/-) and F 12+00 (+/-), approximately 30 to <br />125 feet left of centerline. Structural fill was placed using CAT dozers in 18" to 24" lifts <br />(based on rock size). Moisture conditioning of the fill was performed using a CAT 773-water <br />truck. Each lift was compacted with a 10-ton smooth drum vibratory compactor passing over <br />the entire surface at least 4 times (method compaction technique is applicable). <br />Structural fill was placed between stations 1-19+00 (+/-) and H12+00 (+/-), approximately 50 to <br />100 feet right of centerline. Structural fill was placed using CAT dozers in 18" to 24" lifts <br />(based on rock size). Moisture conditioning of the fill was performed using a CAT 773-water <br />Sheet 2 of 6 <br />VLF Weekly Report WE 07.11.09.D.doc