ame <br />Earth & Environmental <br />Slope scaling was performed between stations A18+00 (+/-) and 26+00 (+/-), approximately 50 <br />to 75 feet right of centerline using a CAT 345 excavator. <br />Drill pattern blasting was performed at the new ADR tank pad excavation. <br />F) Sediment Collection Pond <br />The Sediment pond construction was completed this week. Monday (6/15/2009) the majority <br />of the soil liner fill surface, excluding the southeast corner, was inspected and accepted for <br />riprap placement by an AMEC representative. Riprap was loaded in 40-ton articulating haul <br />trucks at the Arequa process area using a CAT 966 front-end loader. The riprap was placed in a <br />12" lift over the soil liner fill surface using a CAT D-6 dozer. An 18" HDPE pump back tube <br />was placed in the northwest corner prior to riprap placement. Soil liner fill was placed in the <br />southeast corner of the pond when the riprap placement progressed far enough to remove the <br />access ramp in the area. The soil liner fill surface was inspected and accepted by an AMEC <br />representative for riprap placement. Riprap was placed in the southeast corner of the pond in a <br />12" lift using a CAT D-6 dozer. A CAT 966 front-end loader and a John Deere 35D excavator <br />were used to construct a safety berm and clean-up excess construction materials around the <br />pond. <br />G) Material Processing <br />1) South Cresson Clay Processing Area <br />Processing of Soil Liner Fill material continued at the South Cresson Clay Process. A CAT D- <br />6 dozer, a CAT 320 excavator, and a CAT 966 front-end loader were used to process the <br />material. <br />Location This Week <br />tons Cumulative <br />tons Comments <br />So Cresson Cla Processing 4,261 32,774 <br />Squaw Gulch Processing - 35,816 Processing in area com lete. <br />Total 0 63,969 <br />H) Miscellaneous <br />Installation of the LOB Storm Water Culverts continued using a CAT 345 excavator, a jumping <br />jack compactor, and a walk-behind sheep's foot compactor. Fifty four feet of 42" CMP culvert was <br />installed for both culverts (108 feet total). A CAT 345 track excavator was used to excavate a <br />trench for the culvert installation and 6" of pipe bedding material was placed in the trench bottom. <br />The pipe bedding material was moisture conditioned and compacted using a walk-behind sheep's <br />foot compactor. Pipe bedding material was used to backfill each side and between the culverts in <br />12" compacted lifts, bringing the backfill up evenly. The material was moisture conditioned and <br />compacted using a jumping jack compactor and a walk behind sheep's foot compactor. The area <br />was backfilled to two-feet above the installed culverts. Nine nuclear density tests were performed <br />using with results averaging 96% of maximum dry density. Moisture-density relations were <br />performed in accordance with ASTM D-698-07. <br />III) Underground Working <br />A) Drilling <br />No work performed during the week. <br />Sheet 3 of 7 <br />VLF Weekly Report WE 06.20.09.D.doc