amec <br />Earth & Environmental <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: May 9, 2009 <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day/Night <br />Reporting Period: 05/03/09 through 05/09/09 <br />Days S M T W T F S <br />Work Shifts D D D D D D D <br /> - N N N N N - <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 33°F to 36°F (+/-) High: 40° F to 65°F <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: No delays due to weather during the week. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />II) EARTHWORKS <br />A) Clear and Grubbing <br />1) VLF <br />Clearing and grubbing was performed between stations A24+00 (+/-) and A18+00 (+/-), <br />approximately 0 to 100 feet right of centerline, using one CAT 345 excavator. One Volvo 40- <br />ton articulating haul truck transported slash and trees to the Pad 4 slash pile. <br />2) VLF, PSSA Haul Road <br />No work performed during the week. <br />B) Stripping <br />1) VLF <br />Stripping and slope contouring was performed between stations A24+00 (+/-) and A15+00 <br />(+/-) approximately 0 to 150 feet right of centerline, stripping and slope recontouring using a <br />CAT D-10 dozer and one CAT 345 excavator. <br />2) VLF, PSSA Haul Road <br />No work performed during the week. <br />Sheet 1 of 7 <br />VLF Weekly Report WE 05.09.09.D