ameO <br />Eartlt $ En0*0nmantxf <br />VLF EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 <br />Owner: Cripple Creek & Victor Gold Mining Co <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ VLF <br />Date: April 25, 2009 <br />Reporting Period: 04/19/09 through 04/25/09 <br />Project No.: 84201125EO <br />Contractor: Ames Construction Co., Inc. <br />Shift: Day/Night <br />Days S M T W T F S <br />Work Shifts D D D D <br /> N N MN N N <br />D = Day Shift N = Night Shift <br />RECEIVED <br />MAY 01 2009 <br />DivisiOn t and Safety n <br />Ambient Temperature Range (F): Low: 32°F to 36°F (+/-) High: 50° F to 64° F <br />AMEC CQA: Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: No delays due to weather during the week. <br />CONSTRUCTION ACTIVITIES and PROGRESS: <br />1. EARTHWORKS <br />A. Clear and Grubbing <br />1. VLF <br />No work performed during the week. <br />2. VLF, PSSA Haul Road <br />No work performed during the week. <br />B. Stripping <br />1. VLF <br />No work performed during the week. <br />2. VLF, PSSA Haul Road <br />No work performed during the week. <br />C. Waste Rock to Stockpile: <br />1. VLF <br />No work performed during the week. <br />2. VLF, PSSA Haul Road <br />No work performed during the week. <br />Sheet 1 of 6 <br />VLF Weekly Report WE 04.25.09.D.doc