Laserfiche WebLink
• Cresson Project under the MLE is approximately 2012-2032. Table 5-1 provides <br />an overall estimated schedule for construction, operation, and reclamation of the <br />Cresson Project with the inclusion of the MLE facilities. Tables 5-2 and 5-3 <br />provide the sequence of mining and overburden placement, respectively, in each <br />of the mine areas and overburden storage areas by year. Actual development <br />schedules may vary from those presented below and will be reported in the annual <br />report to OMLR. <br />• <br /> <br />Table 5-1 <br />Approximate Time Schedule of Construction, Operations, and Reclamation <br />Activity Duration Start Year Complete Year <br /> in Years <br />Install and Maintain Erosion Controls - Mine 24 Continuing 2032 or when <br />and Overburden Areas revegetation is <br /> established <br />Clear and Grub Mine Areas 7 When 2016 <br /> needed <br /> When <br />Construct Haul Roads 7 2016 <br /> needed <br />Move Utility Lines and Prepare Subgrade for <br /> 1 2009 2009 <br />VLF - Phase V <br />Construct VLF - Phase 5 - Soil Liner Fill 2 2010 2011 <br />Construct VLF - Phase 5 - Liner 1 2011 2011 <br />Mining and Ore Loading 7 Continuing 2016 <br />Mine and Overburden Storage Area <br /> 11 Continuing 2019 <br />Reclamation <br />Crusher and Conveyor Reclamation 1 2017 2018 <br />Complete the Leaching of ore on the VLF 16 Continuing 2024 <br />Complete rinsing and chemical closure of VLF 5 2024 2029 <br />ADR Facilities, Fire Assay/Laboratory, <br /> 1 2029 2030 <br />Maintenance - Reclamation <br />VLF Reclamation 2 2030 2032 <br />Post Closure Monitoring 5 2032 2037 <br />Cripple Creek & Victor Gold Mining Company <br />Cresson Project Mine Life Extension <br />5-4