amec <br />Earth S Environmental <br />3. Sediment Collection Pond <br />Additional rock has been transported to the Joe Dandy Main Cresson backfill. <br />D. Cut to Fill <br />1. VLF <br />No work performed during the week. <br />2. VLF, PSSA Haul Road <br />No work performed during the week. <br />3. Sediment Collection Pond <br />No work performed during the week. <br />E. Subgrade Preparation <br />1. VLF <br />Earlier in the week between stations F10+00 (+/-) and F8+00 (+/-) from 0- 200 feet <br />right of centerline of the North Crest PSSA road, AMES has ripped and prepared the <br />subgrade for structural method specification fill to resume. <br />2. Sediment Collection Pond <br />Slope contouring and subgrade work has been completed during the week. <br />F. SLF Processing (Material is being generated/processed for the LOB and the VLF) <br />Production of the clay material located in SGOSA (Squaw Gulch Overburden Storage <br />Area) Dump 5. <br />The material screening plant located at the AGOSA (Arequa Gulch Overburden Storage <br />Area) completed processing the Drain Cover Fill from material delivered by CC&V Mine. <br />Materials for both the LOB and VLF have resumed production. <br />The mine has transported clay to the South Cresson clay stockpile intermittently throughout <br />the week. <br />Location This Week Cumulative Comments <br /> (tons) (tons) <br />SGOSA Dump 5 Clay <br />Processing 7,572 35,068 Total includes through Apr. 20, `09 <br />Totals 7,572 35,068 <br />G. Miscellaneous <br />Work continued on the 9775 VLF bench widening on the existing Phase IV VLF for the <br />planned relocation of the existing solution lines. Widening of the bench and laying the <br />slopes back to approximately 21-1: IV. Excess ore transported to the Phase IV ore heap <br />using 4-Volvo haul trucks. Work was completed this past Thursday. <br />Sheet 2 of 6 <br />VLF Weekly Report WE 04.18.09.D