3-7 <br />• <br /> <br />• <br />3.2 TOPSOIL REMOVAL AND STORAGE <br />Three soil units occur in the 4.75 acre area of the sediment pond, Construction <br />Material and Topsoil Stockpiles and Coal Mine Waste Pile. The Rivra gravely sand loam <br />variant (.98 acres), Nihill loam (0.3 acres), and Glendive Sandy Loam (3.47 acres). <br />Recommended stripping depths are 12 inches,18 inches, and 24 inches respectively, <br />based upon data presented in Table 4.4-2, Soils Inventory, McClane Canyon Mine <br />(WRDC 1982a). <br />Volumes of topsoil available for stripping and stockpiling have been calculated <br />from the area of the soil mapping units and recommended stripping depths. The topsoil <br />storage area is north of the sediment pond. Vegetation will not be stripped from the <br />storage area prior to stockpiling. The stockpile area is about 30,000 Sq. Ft. (0.7 acre). <br />The volume of material to be stockpiled is about 11,500 CY (including approximately <br />1850 CY in the existing topsoil stockpile that will be moved and combined with the new <br />pile) and the stockpile will reach a height up to 24 feet. <br />Subsoil will be salvaged from the founding of the coal mine waste disposal area <br />and excavation from the Sediment Pond and placed in the construction material <br />stockpile which will have a capacity of approximately 12,000 CY (including <br />approximately 2000 CY in the existing stockpile that will be moved and combined with <br />the new pile). <br />The salvaged soil should have good characteristics. It will be imperfectly mixed, <br />but the soil characteristics are shown below: <br />Characteristic Average Range <br />Texture Scl-SI SI-L <br />Electrical Cond. 0.6 mmhos/cm 0.5 to 0.9 mmhos/cm <br />SAR 1.0 0.2 to 1.3 <br />PH 7.0 6.3 to 8.0 <br />Organic Matter 0.6% 0.2-0.9% <br />Gravels <10% 0-40% <br />Water Availability 0.8 in/in 0.5-1.0 in/in <br />Permeability mod. rapid mod. rapid to rapid <br />Topsoil will be removed by rubber tired scrapers with the assistance of tracked <br />dozers or a track mounted backhoe and truck equipment spread. Topsoil material <br />generated from the initial disturbance will be placed in the stockpiles shown on Figure <br />2.2-3. <br />During storage the topsoil stockpile will be stabilized with the temporary seed mix <br />listed on Table 3.4-2. Weed cover will be controlled via the most appropriate technique, <br />and if the weeds are noxious they will be managed in accordance with Section 4.5.14. <br />This will decrease problems with weed competition during final reclamation. <br />TR-16 M`-Volume 1 <br />(Rev 10/08) <br />