Laserfiche WebLink
Table E-2 Reclamation Timetable <br /> Length of time to <br />Year Phase Comments complete months <br />2009 1 Site Preparation, Topsoil stripping, build stockpiles along the highway. 2 <br />2009- Mine in Mining Area 1, stockpile overburden and topsoil. Build the <br /> 2 isolation berm in the northern portion of the mining areas as shown on Map 10.8 <br />2010 C-2. Seed the stockpiles. <br /> Mine in Mining Area 2, stockpile topsoil and place the overburden <br />2010- encountered on the pit floor and sideslopes in Mining Area 1, where <br /> 3 available, to the elevation and slopes shown on Map F. All remaining 13.0 <br />2011 overburden encountered will be stockpiled. Seed the stockpiles. Bring the <br /> wash plant to the site and create the wash ponds. <br />2011- Mine in Mining Area 3, Stockpile topsoil, place the overburden <br /> 4 encountered on the pit floor and sideslopes to the elevation and slopes 13.1 <br />2012 <br />shown on Map F. <br />2012- Mine in Mining Area 4, place the overburden encountered on the pit floor <br />2013 5 and sideslopes to the elevation and slopes shown on Map F and direct place 17.1 <br /> topsoil in Mining Area 3. Seed the retopsoiled areas. <br /> <br />2013- 6 Mine in Mining Area 5, place the overburden encountered on the pit floor 16.7 <br />2015 and sideslopes to the elevation and slopes shown on Map F and direct place <br /> topsoil in Mining Area 4. Seed all retopsoiled areas. <br /> Mine in Mining Area 6, place the overburden encountered on the pit floor <br />2015- 7 and sideslopes to the elevation and slopes shown on Map F and direct place 20.6 <br />2016 topsoil in Mining Area 5. Reclaim the haul road within Mining Area 5 and <br /> seed the retopsoiled areas. <br /> Mine in Mining Area 7, place the overburden encountered on the pit floor <br />2016- 8 and sideslopes to the elevation and slopes shown on Map F, direct place <br />20.6 <br />2018 topsoil in Mining Area 6. Reclaim the haul road within Mining Area 4 and <br /> seed the retopsoiled areas. <br /> Mine in Mining Area 8, place the overburden encountered on the pit floor <br />2018- 9 and sideslopes to the elevation and slopes shown on Map F, direct place <br />14.3 <br />2019 topsoil in Mining Area 7. Seed the retopsoiled areas. Reclaim the haul road <br /> in Mining Area 3 <br />2019- 10 Remove facilities, use the stockpiles to reclaim Mining Area l and 8, seed 4 <br />2020 newly topsoiled areas. <br /> Total 132.1 <br />Simmons Pit, March 2009 E-3