<br />ameO <br />Earth 8 Environmental <br />LOB EARTHWORKS FIELD MONITORING SUMMARY (WEEKLY REPORT) <br />Project Title: CC&V/ Phase 5 Project No.: 8420125EO <br />Owner: Cripple Creek & Victor Gold Mining Co. Contractor: Ames Construction Co. Inc. <br />Location: Cripple Creek & Victor Gold Mine <br />Work Element: Phase 5 CQA/ LOB <br />Date: 3/07/09 Reporting Period: 03/01/09 through 03/07/09 <br />Days S M T W T F S <br />Work Shifts - D D D D D - <br /> - N N N - - - <br />D = Day Shift N = Night Shift <br />Ambient Temperature Range (F): Low: 25°to 32° High: 33° to 38° <br />AMEC CQA Personnel On-site through the Reporting Period (See Attachment A). <br />AMES: No delays due to weather this week. AMES did not work Thursday or Friday night shifts and did <br />not work Friday day shift due to a company wide training held in Denver Co. <br />CONSTRUCTION ACTIVITIES AND PROGRESS: <br />1. EARTHWORKS <br />A. Clear and Grubbing <br />1. LOB Pad <br />• Minor clean-up work and removal remained to be completed around the <br />mine working # 19. <br />2. LOB/Delivery Road <br />• Work is complete <br />B. Stripping <br />1. LOB Pad <br />• Stripping is complete. Minor cleanup to waste remains around the mine <br />workings #19. <br />2. LOB/Delivery Road <br />• Stripping is complete. Minor cleanup to waste remained. <br />C. Waste Rock to Stockpile <br />1. LOB Pad <br />• A Cat 325 excavator was used in the pad area for removal of all oversize to <br />Dump 4 earlier in the week. Excavation has stopped due to the cut is "non- <br />rippable". Rockbreakers has completed the drilling and blasting of the LOB <br />pad this Thursday. <br />Sheet I of 9 <br />LOB Weekly Report WE 03.07.09.D.doc