My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
2009-03-05_REPORT - M1980244
DRMS
>
Day Forward
>
Report
>
Minerals
>
M1980244
>
2009-03-05_REPORT - M1980244
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/24/2016 3:44:07 PM
Creation date
3/6/2009 1:01:09 PM
Metadata
Fields
Template:
DRMS Permit Index
Permit No
M1980244
IBM Index Class Name
REPORT
Doc Date
3/5/2009
Doc Name
Weekly Construction Quality Assurance ("CQA") Reports
From
CC&V
To
DRMS
Email Name
BMK
Media Type
D
Archive
No
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
49
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
amec <br />Earth & Environmental <br />CQA ACTIVITIES: <br />SUMMARY: <br />Derek Wittwer and Joe Hickey arrived on site from Denver, CO at 10:00AM on January 13, 2009. After <br />attending the weekly construction meeting a site tour was attended with Thomas Sheppard (CC&V). Site <br />mobilization, including site office, and facilities was the primary function through the week. <br />No night shift work was performed during the week. <br />No work was performed on Saturday, January 17. Currently no work activities are planned for Saturdays <br />but Ames has indicated that Saturday will be used as a make up day in the event of delay or stoppage <br />during the current planned work periods Monday to Friday. <br />• Two AMEC Earth and Environmental representatives (Joseph Hickey and Derek Wittwer) attended <br />the weekly construction meeting at 10:00 AM. Construction progress, scheduling, and issues were <br />discussed. <br />• Site specific training was completed by both AMEC representatives. <br />1. Testing Summary <br />No testing was performed at this time. <br />GENERAL PROJECT ITEMS <br />Summary of Concerns: <br />None noted. <br />Summary of Non-conformances: <br />None Issued <br />Summary of Meetings and Discussions: <br />CC& V.• <br />Spoke with Thomas Sheppard concerning the week's mobilization tasks and involvement needed on- <br />site. It was understood that mobilization tasks were the week's main priority and the majority of time <br />would be spent setting up AMEC's facilities. It was also discussed that the majority of the reporting <br />regarding construction activities would not start until Monday January 19, 2009. <br />Spoke with Tom and Ron (CC&V) concerning site activities and mobilization progress. Site <br />introductions for Alfonso Frias occurred on January 16, 2009. <br />Ames Construction: None <br />Amec: None <br />Others: None <br />Sheet 3 of 5 LOB Weekly Report WE 1.17.09.doc
The URL can be used to link to this page
Your browser does not support the video tag.